Line 29: | Line 29: | ||
== Engineering == | == Engineering == | ||
− | - Cathode foils: Roger got an answer from Advanced Circuits that they can't produce the cathode foils because of the big sizes. Roger is still waiting for an independent estimate from them. He submitted to the procurement answers of a second set of questions from them | + | - Cathode foils: Roger got an answer from Advanced Circuits that they can't produce the cathode foils because of the big sizes. Roger is still waiting for an independent estimate from them. He submitted to the procurement answers of a second set of questions from them regarding details of the attempts to find another source. Ross Small from the procurement states that "at this point approval of a sole source is not a sure thing" and he suggested advertising it in the FedBizOps site for 21 days. We discussed what are the pros and cons of such advertising. Pros: no longer sole source and it takes only 21 days. Cons: if some vendors decide to bid they have to prove they can do it and go through the same stages (first article production) as with allflex which will take a lot of time. |
− | - | + | - Some of the fixtures for the wire stringing wre made in the mash shop. |
− | + | David will bring the position measurement system from UVA on Friday (08/27). We will store it in 126. Eugene and Lubomir talked to Nilanga, who promised to work on the MOU with UVA. | |
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
== Full-scale prototype test == | == Full-scale prototype test == |
Revision as of 18:36, 16 September 2010
September 16, 2010 FDC meeting
Tentative Agenda
- Production
- Clean room update
- Electronics: update (Fernando)
- Engineering
- Cathode foil: sole source procurement status (Roger)
- Wire stringing: status and plans (Bill, David)
- Full-scale prototype
- resolution studies (Lubomir) [FDC Log Book, pages 513-514]
- test update (Beni)
- Other