Difference between revisions of "Minutes 11-1-2006"

From GlueXWiki
Jump to: navigation, search
m ((1) moved to Minutes 11-1-2006: Reorganization of page)
Line 8: Line 8:
 
-----------------------------------------------------------------------
 
-----------------------------------------------------------------------
  
1). The meeting was attended by Chuck Hutton and Tim Whitlatch,  
+
1). Project Engineers:
 +
    The meeting was attended by Chuck Hutton and Tim Whitlatch,  
 
     engineers from the Accelerator Group who will be working on the
 
     engineers from the Accelerator Group who will be working on the
 
     FDC system.
 
     FDC system.
Line 16: Line 17:
 
     meetings.
 
     meetings.
  
2). We discussed the time line for completion of the two cathode
+
2). Mechanical Cathode Sandwiches:
 +
    We discussed the time line for completion of the two cathode
 
     mechanical sandwiches.  We want these constructed by the end of
 
     mechanical sandwiches.  We want these constructed by the end of
 
     the year with some flatness measurements completed.
 
     the year with some flatness measurements completed.
Line 25: Line 27:
 
   - Brian will think about the measurement techniques.
 
   - Brian will think about the measurement techniques.
  
3). DSC will talk to Elton about the hours that Brian is working on
+
3). Daughter Boards:
     the project.
+
     DSC will follow up on the ASIC preamp daughter boards.  We need
 
+
4). DSC will follow up on the ASIC preamp daughter boards.  We need
+
 
     to specify the connector size and daughter board size (and
 
     to specify the connector size and daughter board size (and
 
     thickness constraints).
 
     thickness constraints).
  
 
Minutes prepared by Daniel.  Send any comments or corrections along.
 
Minutes prepared by Daniel.  Send any comments or corrections along.

Revision as of 09:09, 13 December 2006

FDC Weekly Meeting

Date: November 1, 2006

Participants: Daniel, Brian, Simon, Chuck Hutton, Tim Whitlatch

Next Meeting: Wednesday, October 8, 2006 @ 1:30 p.m.


1). Project Engineers:

   The meeting was attended by Chuck Hutton and Tim Whitlatch, 
   engineers from the Accelerator Group who will be working on the
   FDC system.
 - Brian gave an overview of the FDC system and the design work.
   They were given the task of producing 3D mechanical drawings of
   the FDC system.  They will have first drawings by our next
   meetings.

2). Mechanical Cathode Sandwiches:

   We discussed the time line for completion of the two cathode
   mechanical sandwiches.  We want these constructed by the end of
   the year with some flatness measurements completed.
 - Brian will find a manufacturer for the full-scale flex boards.
 - Brian will talk to Jeff Wilson about designing the dummy cathode
   boards.
 - The boards need to go out for manufacture within two weeks.
 - Brian will think about the measurement techniques.

3). Daughter Boards:

   DSC will follow up on the ASIC preamp daughter boards.  We need
   to specify the connector size and daughter board size (and
   thickness constraints).

Minutes prepared by Daniel. Send any comments or corrections along.