(Created page with "The goal is to assemble 450 - 500 modules by the end of summer. 64 CRYTUR crystals available (checked) 250 crystals produced by SICCAS, will be in the lab in February 100 P...")
 
 
(15 intermediate revisions by the same user not shown)
Line 1: Line 1:
The goal is to assemble 450 - 500 modules by the end of summer.
+
* Checking crystals
  
64 CRYTUR crystals available (checked) 250 crystals produced by SICCAS, will be in the
+
::: -Visual inspection:  5 min per crystal
lab in February
+
::: -Dimension measurement:  10 min per crystal
 +
::: -Transmission check:  20 min per crystal  (Optional)
 +
::: -Measure light yield using radioactive source:  20 min per crystal (Optional)
 +
::: -Measure light yield using PS setup:  12 modules in the PS setup.
  
100 PMTs are in the lab, expect to receive 400 more by April.
+
* PMT checking
 +
::: -Diameter check
  
 +
* Check PMT divider
 +
::: -Time: 15 min per divider (10 weeks to check 1600 dividers)
 +
::: -University of Regina, GWU, UNCW
  
* Checking crystals
+
* Preparation of silicon cookie
 +
::  - Mix RTV625, remove bubbles
 +
::  - Pour to the gluing fixture  (prepare 36 cookies can order one more fixture)
 +
::  - Set time: 1 day, full cure time: 4 - 5 days
 +
::  - Time: 3 - 4 hours to load the fixture
  
::: Visual inspection  (5 min per crystal)
+
* Check fabricated modules using cosmic ray setup (TBD)
::: Dimension measurement  (10 min per crystal)
+
::: Transmission check (20 min per crystal)
+
::: Light yield (20 min per crystal)
+
 
+
* PMT checking
+
::: Diameter check
+
::: Check gains (perform check on some randomly selected sample)
+
  
  
  
 
=== Module Fabrication ===
 
=== Module Fabrication ===
 
 
  
 
* Brazing straps
 
* Brazing straps
::: Procedure - brazing setup exists, has to be finalized
+
::: Time per module: 20 min
::: Time per module - 30 min
+
 
+
  
 
* ESR shaping  
 
* ESR shaping  
:: - ESR cutting   (cutting tool exist)
+
:: - ESR cutting
:: - Shape in the oven (2 tools exist, 30 min per cycle]
+
:: - Shape in the oven (2 tools exist, 20 min per cycle]
 
+
:: - Time per module: 20 min
 
+
* Tedlar cutting
+
:: - Tool exists
+
:: - Time per module - 15 min
+
  
 +
* Glue light guide to the PMT using UV glue
 +
:: - Time per module: 10 min
  
 
* Crystal wrapping  
 
* Crystal wrapping  
:: - Tool exists
+
:: - Cut ESR and Tedlar
:: - Time per module - 20 min
+
:: - Wrap module
 +
:: - Time per module: 20 min
  
 +
* Module fabrication
 +
:: - Insert mu-metal shield
 +
:: - Attach PMT housing, set tension screws
 +
:: - Insert PMT with silicon cookies, set tension plate
 +
:: - Time per module: 30 min
  
* Preparation of silicon cookie
 
::  - Tool in preparation
 
::  - Mix RTV
 
::  - Pour to the gluing fixture
 
::  - wait 1 day to set, move to the oven for several hours
 
::  - Time:  2-3 days per 30 cookies
 
  
 
+
:: '''Total fabrication time:  1 hour 40 min per module'''
* Module fabrication
+
::::::::                            (~5 modules a day, 100 modules a month)
:: - Time per module: 30 min
+

Latest revision as of 13:26, 22 April 2021

  • Checking crystals
-Visual inspection: 5 min per crystal
-Dimension measurement: 10 min per crystal
-Transmission check: 20 min per crystal (Optional)
-Measure light yield using radioactive source: 20 min per crystal (Optional)
-Measure light yield using PS setup: 12 modules in the PS setup.
  • PMT checking
-Diameter check
  • Check PMT divider
-Time: 15 min per divider (10 weeks to check 1600 dividers)
-University of Regina, GWU, UNCW
  • Preparation of silicon cookie
- Mix RTV625, remove bubbles
- Pour to the gluing fixture (prepare 36 cookies can order one more fixture)
- Set time: 1 day, full cure time: 4 - 5 days
- Time: 3 - 4 hours to load the fixture
  • Check fabricated modules using cosmic ray setup (TBD)


Module Fabrication

  • Brazing straps
Time per module: 20 min
  • ESR shaping
- ESR cutting
- Shape in the oven (2 tools exist, 20 min per cycle]
- Time per module: 20 min
  • Glue light guide to the PMT using UV glue
- Time per module: 10 min
  • Crystal wrapping
- Cut ESR and Tedlar
- Wrap module
- Time per module: 20 min
  • Module fabrication
- Insert mu-metal shield
- Attach PMT housing, set tension screws
- Insert PMT with silicon cookies, set tension plate
- Time per module: 30 min


Total fabrication time: 1 hour 40 min per module