The goal is to assemble 450 - 500 modules by the end of summer.
+
* Checking crystals
  
64 CRYTUR crystals available (checked) 250 crystals produced by SICCAS, will be in the
+
::: -Visual inspection:  5 min per crystal
lab in February
+
::: -Dimension measurement:  10 min per crystal
 +
::: -Transmission check:  20 min per crystal  (Optional)
 +
::: -Measure light yield using radioactive source:  20 min per crystal (Optional)
 +
::: -Measure light yield using PS setup:  12 modules in the PS setup.
  
100 PMTs are in the lab, expect to receive 400 more by April.
+
* PMT checking
 +
::: -Diameter check
  
 +
* Check PMT divider
 +
::: -Time: 15 min per divider (10 weeks to check 1600 dividers)
 +
::: -University of Regina, GWU, UNCW
  
* Checking crystals
+
* Preparation of silicon cookie
 +
::  - Mix RTV625, remove bubbles
 +
::  - Pour to the gluing fixture  (prepare 36 cookies can order one more fixture)
 +
::  - Set time: 1 day, full cure time: 4 - 5 days
 +
::  - Time: 3 - 4 hours to load the fixture
  
::: Visual inspection  (5 min per crystal)
+
* Check fabricated modules using cosmic ray setup (TBD)
::: Dimension measurement  (10 min per crystal)
+
::: Transmission check (20 min per crystal)
+
::: Light yield (20 min per crystal)
+
 
+
* PMT checking
+
::: Diameter check
+
::: Check gains (perform check on some randomly selected sample)
+
  
  
Line 23: Line 27:
  
 
* Brazing straps
 
* Brazing straps
::: Time per module - 20 min
+
::: Time per module: 20 min
  
 
* ESR shaping  
 
* ESR shaping  
 
:: - ESR cutting
 
:: - ESR cutting
 
:: - Shape in the oven (2 tools exist, 20 min per cycle]
 
:: - Shape in the oven (2 tools exist, 20 min per cycle]
:: - Time per module - 20 min
+
:: - Time per module: 20 min
 +
 
 +
* Glue light guide to the PMT using UV glue
 +
:: - Time per module: 10 min
  
 
* Crystal wrapping  
 
* Crystal wrapping  
 
:: - Cut ESR and Tedlar
 
:: - Cut ESR and Tedlar
 
:: - Wrap module  
 
:: - Wrap module  
:: - Time per module - 20 min
+
:: - Time per module: 20 min
  
 
* Module fabrication
 
* Module fabrication
Line 42: Line 49:
  
  
:: '''Total fabrication time:  1.5 hours per module'''
+
:: '''Total fabrication time:  1 hour 40 min per module'''
:: (5 modules a day, 100 a month)  
+
::::::::                            (~5 modules a day, 100 modules a month)
 
+
* Preparation of silicon cookie
+
::  - Mix RTV625, remove bubbles
+
::  - Pour to the gluing fixture  (36 cookies can order one more)
+
::  - Set time: 1 day, full cure time: 4 - 5 days
+
::  - Time: 3 - 4 hours
+

Latest revision as of 13:26, 22 April 2021

  • Checking crystals
-Visual inspection: 5 min per crystal
-Dimension measurement: 10 min per crystal
-Transmission check: 20 min per crystal (Optional)
-Measure light yield using radioactive source: 20 min per crystal (Optional)
-Measure light yield using PS setup: 12 modules in the PS setup.
  • PMT checking
-Diameter check
  • Check PMT divider
-Time: 15 min per divider (10 weeks to check 1600 dividers)
-University of Regina, GWU, UNCW
  • Preparation of silicon cookie
- Mix RTV625, remove bubbles
- Pour to the gluing fixture (prepare 36 cookies can order one more fixture)
- Set time: 1 day, full cure time: 4 - 5 days
- Time: 3 - 4 hours to load the fixture
  • Check fabricated modules using cosmic ray setup (TBD)


Module Fabrication

  • Brazing straps
Time per module: 20 min
  • ESR shaping
- ESR cutting
- Shape in the oven (2 tools exist, 20 min per cycle]
- Time per module: 20 min
  • Glue light guide to the PMT using UV glue
- Time per module: 10 min
  • Crystal wrapping
- Cut ESR and Tedlar
- Wrap module
- Time per module: 20 min
  • Module fabrication
- Insert mu-metal shield
- Attach PMT housing, set tension screws
- Insert PMT with silicon cookies, set tension plate
- Time per module: 30 min


Total fabrication time: 1 hour 40 min per module