(Created page with "The goal is to assemble 450 - 500 modules by the end of summer. 64 CRYTUR crystals available (checked) 250 crystals produced by SICCAS, will be in the lab in February 100 P...")
 
(Module Fabrication)
Line 21: Line 21:
  
 
=== Module Fabrication ===
 
=== Module Fabrication ===
 
 
  
 
* Brazing straps
 
* Brazing straps
::: Procedure - brazing setup exists, has to be finalized
+
::: Time per module - 20 min
::: Time per module - 30 min
+
 
+
  
 
* ESR shaping  
 
* ESR shaping  
:: - ESR cutting   (cutting tool exist)
+
:: - ESR cutting
 
:: - Shape in the oven (2 tools exist, 30 min per cycle]
 
:: - Shape in the oven (2 tools exist, 30 min per cycle]
 +
:: - Time per module - 20 min
  
 +
* Crystal wrapping
 +
:: - Cut ESR and Tedlar
 +
:: - Wrap module
 +
:: - Time per module - 20 min
  
* Tedlar cutting
+
* Module fabrication
:: - Tool exists
+
:: - Insert mu-metal shield
:: - Time per module - 15 min
+
:: - Attach PMT housing, set tension screws
 +
:: - Insert PMT with silicon cookies, set tension plate
 +
:: - Time per module: 30 min
  
 
* Crystal wrapping
 
:: - Tool exists
 
:: - Time per module - 20 min
 
  
  
 
* Preparation of silicon cookie
 
* Preparation of silicon cookie
::  - Tool in preparation
+
::  - Mix RTV625, remove bubbles
::  - Mix RTV
+
 
::  - Pour to the gluing fixture
 
::  - Pour to the gluing fixture
::  - wait 1 day to set, move to the oven for several hours
+
::  - Set time 1 day, full cure time: 4 - 5 days  
:- Time:  2-3 days per 30 cookies
+
:: -
 
+
 
+
* Module fabrication
+
:: - Time per module: 30 min
+

Revision as of 12:49, 22 April 2021

The goal is to assemble 450 - 500 modules by the end of summer.

64 CRYTUR crystals available (checked) 250 crystals produced by SICCAS, will be in the lab in February

100 PMTs are in the lab, expect to receive 400 more by April.


  • Checking crystals
Visual inspection (5 min per crystal)
Dimension measurement (10 min per crystal)
Transmission check (20 min per crystal)
Light yield (20 min per crystal)
  • PMT checking
Diameter check
Check gains (perform check on some randomly selected sample)


Module Fabrication

  • Brazing straps
Time per module - 20 min
  • ESR shaping
- ESR cutting
- Shape in the oven (2 tools exist, 30 min per cycle]
- Time per module - 20 min
  • Crystal wrapping
- Cut ESR and Tedlar
- Wrap module
- Time per module - 20 min
  • Module fabrication
- Insert mu-metal shield
- Attach PMT housing, set tension screws
- Insert PMT with silicon cookies, set tension plate
- Time per module: 30 min


  • Preparation of silicon cookie
- Mix RTV625, remove bubbles
- Pour to the gluing fixture
- Set time 1 day, full cure time: 4 - 5 days
-