The goal is to assemble 450 - 500 modules by the end of summer.
 
  
64 CRYTUR crystals available (checked) 250 crystals produced by SICCAS, will be in the
 
lab in February
 
 
100 PMTs are in the lab, expect to receive 400 more by April.
 
  
  
 
* Checking crystals
 
* Checking crystals
  
::: Visual inspection (5 min per crystal)
+
::: Visual inspection5 min per crystal
::: Dimension measurement (10 min per crystal)
+
::: Dimension measurement10 min per crystal
::: Transmission check (20 min per crystal)
+
::: Transmission check20 min per crystal (Optional)
::: Light yield (20 min per crystal)
+
::: Measure light yield using radioactive source:  20 min per crystal (Optional)
 +
::: Measure light yield using PS setup:  12 modules in the PS setup.
  
 
* PMT checking  
 
* PMT checking  
 
::: Diameter check  
 
::: Diameter check  
::: Check gains (perform check on some randomly selected sample)
+
 
 +
 
 +
* Preparation of silicon cookie
 +
:: - Mix RTV625, remove bubbles
 +
::  - Pour to the gluing fixture  (prepare 36 cookies can order one more fixture)
 +
::  - Set time: 1 day, full cure time: 4 - 5 days
 +
::  - Time: 3 - 4 hours to load the fixture
  
  
Line 43: Line 45:
  
 
:: '''Total fabrication time:  1.5 hours per module'''
 
:: '''Total fabrication time:  1.5 hours per module'''
::::::::                            (5 modules a day, 100 modules a month)  
+
::::::::                            (5 modules a day, 100 modules a month)
 
+
* Preparation of silicon cookie
+
::  - Mix RTV625, remove bubbles
+
::  - Pour to the gluing fixture  (prepare 36 cookies can order one more fixture)
+
::  - Set time: 1 day, full cure time: 4 - 5 days
+
::  - Time: 3 - 4 hours to load the fixture
+

Revision as of 13:09, 22 April 2021


  • Checking crystals
Visual inspection: 5 min per crystal
Dimension measurement: 10 min per crystal
Transmission check: 20 min per crystal (Optional)
Measure light yield using radioactive source: 20 min per crystal (Optional)
Measure light yield using PS setup: 12 modules in the PS setup.
  • PMT checking
Diameter check


  • Preparation of silicon cookie
- Mix RTV625, remove bubbles
- Pour to the gluing fixture (prepare 36 cookies can order one more fixture)
- Set time: 1 day, full cure time: 4 - 5 days
- Time: 3 - 4 hours to load the fixture


Module Fabrication

  • Brazing straps
Time per module - 20 min
  • ESR shaping
- ESR cutting
- Shape in the oven (2 tools exist, 20 min per cycle]
- Time per module - 20 min
  • Crystal wrapping
- Cut ESR and Tedlar
- Wrap module
- Time per module - 20 min
  • Module fabrication
- Insert mu-metal shield
- Attach PMT housing, set tension screws
- Insert PMT with silicon cookies, set tension plate
- Time per module: 30 min


Total fabrication time: 1.5 hours per module
(5 modules a day, 100 modules a month)