Difference between revisions of "Nov 3-5, 2009 Calorimetry"

From GlueXWiki
Jump to: navigation, search
(2:00 Contract Requirements)
(Tuesday Nov 3)
Line 37: Line 37:
 
## Depart: DL flight 3622 Thu Nov 5 at 06:53 AM
 
## Depart: DL flight 3622 Thu Nov 5 at 06:53 AM
  
== Tuesday Nov 3 ==  
+
== Tuesday Nov 3 ==
 +
 
 +
=== 4:30 Visit to University ==
  
 
== Wednesday Nov 4 (Regina times, JLab is one hour later) ==
 
== Wednesday Nov 4 (Regina times, JLab is one hour later) ==

Revision as of 14:54, 27 October 2009

BCAL Fabrication Readiness Review

  • ESNET and EVO session
  • Phone only if requested:
    • +1-800-377-8846 : US
    • +1-888-276-7715 : Canada
    • +1-302-709-8424 : International
    • then enter participant code: 77438230# (remember the "#"). Phone line by request only.

Topics/Issues that need discussion/resolution

  1. schedule, revision of any milestones based on present projections
  2. shipping
    1. handling of crates/number of crates to build
    2. timing of shipments including considerations of winter weather
  3. Lessons learned from construction prototype
  4. Training of personnel, especially transitions between work periods
  5. testing
  6. Billing and invoicing guidelines
  7. JLab:
    1. Information/feedback required from JLab?
    2. Plan for storage space at JLab for completed modules
    3. Plan at JLab for testing of finished modules?

Documents to Review

  1. Regina Bcal Web Page
  2. Bcal Fabrication Reports
  3. Nov 3-5, 2009 Calorimetry Backup

Tentative Agenda

Itineraries (Note: Regina is one hour behind of Newport News)

  1. Elton Smith and Tim Whitlatch:
    1. Arrive: UA flight 5806 Tue Nov 3 at 03:05 PM.
    2. Depart: AC flight 1116 Thu Nov 5 at 11:25 AM
  2. Bruce Lenzer and Michael Martin:
    1. Arrive: DL flight 2628 Tue Nov 3 at 01:48 PM
    2. Depart: DL flight 3622 Thu Nov 5 at 06:53 AM

Tuesday Nov 3

= 4:30 Visit to University

Wednesday Nov 4 (Regina times, JLab is one hour later)

8:30 Arrival

9:00 Tour

  1. Lead swaging
  2. Fiber sorting
  3. Fiber testing
  4. Matrix assembly

10:00- 12:00 Discussion

  1. Status of project
  2. Lessons learned from construction prototype
  3. Training of personnel, especially transitions between work periods
  4. Testing
    1. Fibers
    2. lead
    3. matrix
  5. Shipping
    1. storage requirements at Regina and JLab
    2. handling of crates/number of crates to build
    3. timing of shipments including considerations of winter weather
  6. Schedule
    1. Official schedule and tracking

12:00 lunch

2:00 Contract Requirements

  1. Final Construction Plan
  2. Final Acceptance Test Plan
  3. Quality Assurance Plan
  4. Schedule
  5. Billing and invoicing

Thursday Nov 5