* Reviewed minutes from last meeting
 
* Looked at Sasha's installation wiki page
 
** Showed different possible damage to wrapping of existing lead glass modules
 
** Is aluminum being stuck to module surface a performance issue (light yield)?
 
*** Really no way to test now
 
*** Need to decide threshold for re-wrapping
 
** Some inspection/labelling needed prior to unstacking of blocks
 
** Sasha proposed that him and Arshak inspect each module after removal to decide on action to be taken -
 
** Mark and Malte need to be in loop for base and pmt changes
 
*** Possibly test light yield on first 100
 
** Malte asked who unstacked the original modules from BNL and what were the issues
 
** Looks like we will have about 500 good PMT spares
 
** Sasha presented manpower requirements
 
*** would need 2 students for 30 weeks to re-wrap all old modules
 
*** Total 11 students for 3 months will be needed for project (Eugene to check budgets)
 
*** JLAB folks responsible for unstacking modules - Hall D Techs/DSG?
 
*** Sasha/Arshak would train students to do module refurb
 
*** Students would label and bundle cables
 
*** JLAB tech staff handle structure, darkroom, cable trays, racks
 
*** JLAB electronics group handle crate installation and cabling possibly with help from DSG
 
*** Students would handle moving existing cables to adjacent crates on north and south racks
 
*** Need to get a final list of universities supplying students
 
*** Maybe best to downgrade the hall from RAD worker 1 to Gert only
 
** Sasha mentioned the need to re-strap some existing 25 micron brass strap crystal modules
 
** Need to start developing procedures for all aspects of the project
 
** Need to define workstations needed - add to Sasha's table and develop a layout
 
* Need to have electric power added to south side of FCAL platform
 
* Need to update strawman schedule with more detail including resources
 
* Lead glass acrylic sheet same design as original - need to remake panes for new geometry
 
  
 
== Action Items ==
 
== Action Items ==
* Develop required work stations needed and add to table - Sasha
 
* Develop hall layout based on work stations - Tim/Stephanie
 
* Update Gant chart with more detail and resources - Scot/Tim
 
* Check to see if hall can be downgraded to a Radiologically Controlled area - Tim
 
* Start developing procedures - Sasha - Tim
 
* Determine what universities/students will be available - Sasha
 
* Have electricians look at bringing power to new racks on south side - Tim
 
* Determine if we have budget for students - Eugene
 
* Design patch panels - Chris S./Stephanie
 

Revision as of 08:44, 15 November 2022

Meeting Time and Place

Wednesday November 16, 2022 10am At Jefferson Lab, Hall D Counting House and on Teams

Agenda

Both step.jpeg
JBweld cooling test.jpeg
Glass module steps.jpeg

Minutes

Action Items