Difference between revisions of "November 18, 2011 Design Meeting"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 8: Line 8:
 
** Walkthrough punchlist/Beneficial occupancy - Dec 1
 
** Walkthrough punchlist/Beneficial occupancy - Dec 1
 
** Hall D open house Dec 2
 
** Hall D open house Dec 2
* Vacation Donation
+
** Vacation Donation
 
** Presentations available M:\halld\Engineering\Presentations
 
** Presentations available M:\halld\Engineering\Presentations
 
**  training - up to date?
 
**  training - up to date?

Revision as of 08:22, 18 November 2011

Friday Nov 18, 2011 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 231

Agenda

  • ESH&Q minute - animal safety
  • Announcements
    • Appraisals status
    • Walkthrough punchlist/Beneficial occupancy - Dec 1
    • Hall D open house Dec 2
    • Vacation Donation
    • Presentations available M:\halld\Engineering\Presentations
    • training - up to date?
  • CAD update
  • Upstream platform install Status - Tom
  • Solenoid Install/Interface
  • FDC construction update - Bill
  • Large Vacuum chamber specs
  • Target update
  • BCAL readout update
  • Collimator beamline update
  • Downstream/Solenoid Platforms update
  • Mock up update -
  • Spare solenoid
  • Fabrication/installation work - Tom

Outstanding Action Items

  • Discuss with Eugene who owner of Counting house will be - Hovannes has been assigned
  • Get with Tom on Beamline fab tasks - Slava
  • Post .pdf manpower assignments on M drive - Tim

Minutes

    • In attendance W. Crahen, J. Fochtman, V. Razmyslovich, J. Lagner, G. Browns, R. Getz, W. Sachleben, Tim Whitlatch, J. Conger, C. Hutton