Meeting Time and Place
Thursday November 18, 2021, 3:00pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/November_04,_2021_CPP_Design_Meeting
- Testing status - Beni/Elton
- LV boxes https://logbooks.jlab.org/entry/3939570
- Moving of Vertical cable trays and cables inside
- Design/Fab/Procurement status
- Lead absorbers - awarded
- All assembly hardware either here or due in by December
- Test install in the TEDF High bay - use of 2 or 3 chambers
File:Cpp install assy.pdf
- Installation/assy 3D Model and dwgs
- DS Chamber orientation
- Scintillator orientation
- assembly components - drawings released
- Installation drawings in review
- Target Design in work
- Things to work out
- Gas system, manifold/bubblers (Beni has some)
- Complete structural analysis - approved by Tom Renzo - need to release into system
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
- Modified US vacuum system
- Solid target installation
- Installation drawing including Microscope move
- CPP Detector operations in Hall D OSP
- Possible use of nitrogen flow for cooling electronics in Faraday cage