(Created page with "== Meeting Information == GlueX DIRC Meeting<br> Monday November 19, 2018<br> 1:00 pm, EDT<br> JLab room A110<br> == Connection Using Bluejeans == # To join via Polycom room...") |
(→Agenda) |
||
Line 21: | Line 21: | ||
#* Fabrication status update (Ernie and Jason) | #* Fabrication status update (Ernie and Jason) | ||
#** Box window flange modification at Lesker (Ernie/Tim) | #** Box window flange modification at Lesker (Ernie/Tim) | ||
− | #*** Lower (beam right) box machining completed: flat to +/- 0.15 mm (0.006'') | + | #*** Lower (beam right) box machining completed: flat to +/- 0.15 mm (0.006''). Shipping back from Lesker today. |
− | #*** Upper (beam left) at Lesker for modification | + | #*** Upper (beam left) at Lesker for modification now. |
#** LED fiber feedthroughs and diffuser | #** LED fiber feedthroughs and diffuser | ||
#*** ThorLab diffuser and fiber coupling tests (Bill) | #*** ThorLab diffuser and fiber coupling tests (Bill) | ||
− | #*** Diffuser location and | + | #*** Diffuser location and projected angles (Stephanie) |
#** Dark box enclosure: fabrication, testing, and delivery to JLab (Jason) | #** Dark box enclosure: fabrication, testing, and delivery to JLab (Jason) | ||
− | #** Quartz window RTV | + | #** Quartz window RTV after measurement of lower box at JLab. Delivery schedule? (Ernie) |
#* Testing in EEL 226 | #* Testing in EEL 226 | ||
#** [https://halldweb.jlab.org/wiki/images/5/50/GLUEX_Lightbox_LH_Assy_CABLING.PDF Darkbox cabling from Jason] | #** [https://halldweb.jlab.org/wiki/images/5/50/GLUEX_Lightbox_LH_Assy_CABLING.PDF Darkbox cabling from Jason] |
Revision as of 09:51, 19 November 2018
Meeting Information
GlueX DIRC Meeting
Monday November 19, 2018
1:00 pm, EDT
JLab room A110
Connection Using Bluejeans
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
- To join via phone, use one of the following numbers and the Conference ID: 846453895
- US or Canada: +1 408 740 7256 or
- US or Canada: +1 888 240 2560
- More information on connecting to bluejeans is available.
Agenda
- Announcements
- All components need to be at JLab and tested by end of December, in preparation for January install
- Optical box
- Fabrication status update (Ernie and Jason)
- Box window flange modification at Lesker (Ernie/Tim)
- Lower (beam right) box machining completed: flat to +/- 0.15 mm (0.006). Shipping back from Lesker today.
- Upper (beam left) at Lesker for modification now.
- LED fiber feedthroughs and diffuser
- ThorLab diffuser and fiber coupling tests (Bill)
- Diffuser location and projected angles (Stephanie)
- Dark box enclosure: fabrication, testing, and delivery to JLab (Jason)
- Quartz window RTV after measurement of lower box at JLab. Delivery schedule? (Ernie)
- Box window flange modification at Lesker (Ernie/Tim)
- Testing in EEL 226
- Darkbox cabling from Jason
- Cabling tests and plans for dark box tests (Bill/Andrew)
- Fabrication status update (Ernie and Jason)
- PMT fit results (Andrew)
- Software/simulations
- Addressing ERR review recommendations
- Recommendations pertaining to DIRC commissioning should be addressed before installation.
- AOB