Difference between revisions of "November 4, 2011 Design Meeting"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Minutes)
Line 39: Line 39:
  
  
**In attendance W. Crahen,  J. Fochtman,  V. Razmyslovich, J. Lagner, G. Biallas, R. Getz,    W. Sachleben,  Tim Whitlatch,  J. Conger, C. Hutton
+
**In attendance W. Crahen,  J. Fochtman,  V. Razmyslovich, J. Lagner, G. Browns, R. Getz,    W. Sachleben,  Tim Whitlatch,  J. Conger, C. Hutton

Revision as of 07:55, 4 November 2011

Friday Nov 04, 2011 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 231

Agenda

  • ESH&Q minute - safety observations
  • Announcements
    • Giles Brown
    • Appraisals status
    • Walkthrough punchlist/Beneficial occupancy - Dec 1
    • Collaboration meeting OCT 3
    • Lehman review Oct 20
    • Lab budget 3 months good
    • JLAB Strategic planning
    • Presentations available M:\halld\Engineering\Presentations
    • training - up to date?
  • CAD update
  • Solenoid install Status - Josh
  • TOF/Start counter update
  • FDC construction update - Bill
  • Tagger Magnet/vacuum chamber
  • Target update
  • BCAL readout update
  • CDC update
  • Collimator beamline update
  • Platforms update
  • Mock up update -
  • Beamline update
  • BCAL assy update
  • Spare solenoid
  • Fabrication/installation work - Tom

Outstanding Action Items

  • Change Design standards document to include Analysis designation (A001) - Chuck
  • Update drawing check list to compare dwg and 3D model (any non-parametric dimensions)
  • Post manpower assignments on M drive - Tim

Minutes

    • In attendance W. Crahen, J. Fochtman, V. Razmyslovich, J. Lagner, G. Browns, R. Getz, W. Sachleben, Tim Whitlatch, J. Conger, C. Hutton