(Tentative Schedule)
Line 15: Line 15:
 
#DRAFT Construction procedures
 
#DRAFT Construction procedures
 
#[http://www.jlab.org/~whitey/BCAL/WEDGE_Oct8-2008.pdf  Wedge Detail Drawing]
 
#[http://www.jlab.org/~whitey/BCAL/WEDGE_Oct8-2008.pdf  Wedge Detail Drawing]
 
= Agenda Items=
 
# Construction manager
 
# Review of schedule
 
#* Sequence of events
 
#* Receipt/QA of fibers
 
#* Receipt/QA and swaging of lead
 
#* Production
 
#* QA of module production
 
#* Shipping/receiving
 
#* Reporting
 
# Space allocation
 
# Hiring, supervising hourly labor
 
# Construction MOUs with UofR and UofA
 
  
 
=Tentative Schedule=
 
=Tentative Schedule=
 
#Jlab: Arrival: Tuesday, early afternoon. Departure: Thursday, midday.
 
#Jlab: Arrival: Tuesday, early afternoon. Departure: Thursday, midday.
 
#UofR: Arrival Tuesday, late afternoon; Departure: Thursday, midday.
 
#UofR: Arrival Tuesday, late afternoon; Departure: Thursday, midday.
=Agenda for Wednesday=
+
 
#....
+
  
 
=Participants=
 
=Participants=
Line 51: Line 36:
 
#* Doug Gingrich, CPP Director
 
#* Doug Gingrich, CPP Director
 
#* John Beamish, Physics dept chair
 
#* John Beamish, Physics dept chair
 +
 +
 +
=Agenda for Wednesday=
 +
#....
 +
 +
= Agenda Items=
 +
# Construction manager
 +
# Review of schedule
 +
#* Sequence of events
 +
#* Receipt/QA of fibers
 +
#* Receipt/QA and swaging of lead
 +
#* Production
 +
#* QA of module production
 +
#* Shipping/receiving
 +
#* Reporting
 +
# Space allocation
 +
# Hiring, supervising hourly labor
 +
# Construction MOUs with UofR and UofA
 +
  
 
=Minutes=
 
=Minutes=
 
Attending:
 
Attending:

Revision as of 14:38, 9 October 2008

Supporting Documents and References

  1. DRAFT Construction Schedule
  2. Fiber Specifications
  3. DRAFT Lead Specifications
  4. DRAFT Construction Manager Job Description
  5. DRAFT Fiber QA and acceptance
  6. DRAFT Lead QA and acceptance
  7. DRAFT Construction procedures
  8. Wedge Detail Drawing

Tentative Schedule

  1. Jlab: Arrival: Tuesday, early afternoon. Departure: Thursday, midday.
  2. UofR: Arrival Tuesday, late afternoon; Departure: Thursday, midday.


Participants

  1. Jefferson Lab
    • Elke Aschenauer, Hall D group Leader
    • Tim Whitlatch, Hall D engineer
    • Elton Smith, Hall D scientist
  2. University of Regina
    • George Lolos, GlueX co-spokesperson
    • Zisis Papandreu, Bcal Working Group
    • Andrei Semenov, Bcal Working Group
  3. University of Alberta
    • Jim Pinfold, GlueX contact
    • Jan Soukup, Engineer
    • Gilbert Lachat, Machine shop director
    • Doug Gingrich, CPP Director
    • John Beamish, Physics dept chair


Agenda for Wednesday

  1. ....

Agenda Items

  1. Construction manager
  2. Review of schedule
    • Sequence of events
    • Receipt/QA of fibers
    • Receipt/QA and swaging of lead
    • Production
    • QA of module production
    • Shipping/receiving
    • Reporting
  3. Space allocation
  4. Hiring, supervising hourly labor
  5. Construction MOUs with UofR and UofA


Minutes