Oct 18, 2011 SiPM Electrical and Cooling

From GlueXWiki
Revision as of 17:57, 20 September 2012 by Elton (Talk | contribs) (Action Items from previous meetings)

Jump to: navigation, search

Action Items from previous meetings

  1. Decide on cable connections for monitoring cable from Bcal wedge to patch panel. Consider electronics needed for pulsing system (Elton and Fernando)
  2. Work with Shaun to write up a procedure for substituting a sensor on one of the boards to be assembled. (Jack)
  3. Provide feedback to Fernando on his readout assembly schedule (Elton and Jim)
  4. Check uniformity of LED source in black testing box
  5. Make a metal die to punch holes in cooling mat to ease assembly. (Nick and Jim)
  6. Send P6 line numbers (and accounts) to Jim for purchase of the mechanical parts (Elton).

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule, reporting, and manpower (Elton)
  4. mini-Bcal (Elton)
  5. SiPM production testing (Yi)
  6. Mechanical assembly (Jim)
  7. Temperature compensation (Jack)
  8. Electronic boards (Fernando and Chris)
  9. Light guide gluing setup (Scot)

Minutes

Attending: