Difference between revisions of "October 14, 2010 Des/Fab Meeting"

From GlueXWiki
Jump to: navigation, search
 
(Agenda)
 
(2 intermediate revisions by the same user not shown)
Line 16: Line 16:
 
* FDC construction preparations
 
* FDC construction preparations
 
* Cryo transfer line update
 
* Cryo transfer line update
* Space issues
+
* Space issues (ESB ready to populate
* Manpower
+
* Manpower (Eng,Tech,Des)
  
 
==Outstanding Action Items==
 
==Outstanding Action Items==
* Determine new positions of cryo transfer line supports and feedback to civil (Jim/Tim)* Under work - needs to be settled within the next few weeks
+
* <strike>Determine new positions of cryo transfer line supports and feedback to civil (Jim/Tim)* Under work - needs to be settled within the next few weeks </strike>
 
* Need to develop a leak check and assy plan for cryo lines (Jim/Tom) in work
 
* Need to develop a leak check and assy plan for cryo lines (Jim/Tom) in work
 
* Identify PLC programmer to take over for Mark Wissman (Tim)
 
* Identify PLC programmer to take over for Mark Wissman (Tim)
 
* Set up for Dave to give presentation on FDC procedures at a later meeting (Tim)
 
* Set up for Dave to give presentation on FDC procedures at a later meeting (Tim)
* Tom to come up with a list of equipment needed.
+
* <strike>Tom to come up with a list of equipment needed. </strike>
 +
* Complete OSP for solenoid test (all)
  
 
==Discussions==
 
==Discussions==

Latest revision as of 07:31, 14 October 2010

Meeting Time and Place

Thursday Oct 14, 2010 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 428

Agenda

  • ESH&Q minute (Solenoid test THA)
  • Announcements
    • Evaluations
    • training
  • Upcoming reviews *
  • Installation Schedule
  • Solenoid Test Status *
  • Civil construction Status *
  • Tagger magnet status
  • FDC construction preparations
  • Cryo transfer line update
  • Space issues (ESB ready to populate
  • Manpower (Eng,Tech,Des)

Outstanding Action Items

  • Determine new positions of cryo transfer line supports and feedback to civil (Jim/Tim)* Under work - needs to be settled within the next few weeks
  • Need to develop a leak check and assy plan for cryo lines (Jim/Tom) in work
  • Identify PLC programmer to take over for Mark Wissman (Tim)
  • Set up for Dave to give presentation on FDC procedures at a later meeting (Tim)
  • Tom to come up with a list of equipment needed.
  • Complete OSP for solenoid test (all)

Discussions

    • In attendance W. Crahen, G. Biallas, J. Fochtman, T. Carstens, C. Hutton, V. Razmyslovich, J. Lagner, F. Martin, R. Getz, J. Foyles, M. Stevens, R. Bunton, G. Humble, C. Heck, D. Butler, K. Sullivan, Josh Ballard, W. Sachleben, Paul Collins, Tim Whitlatch

Action Items