Friday August 5, 2011 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 231

Agenda

  • ESH&Q minute "dumb" waiters
  • Announcements
    • training - up to date
    • Appraisal calender
    • Budgets
    • Lehman review
    • HDLisT
  • Solenoid install Status - Josh
  • FDC construction update - Dave
  • Detector Cable Mock up update -Tom
  • BCAL assy test setup - Tim
  • Civil update - M:\facilities\Projects\12_GeV\Construction\Hall_D\Photos\Sept_2011
  • Fabrication/installation work - Tom
  • scheduled work - J:\Hall D\schedules and budgets\manpower assignments

Old Action Items

  • Work out mock up with John/Tom
  • Get fdc and cdc hardware for mock up made - Tim/John
  • Modify rigging contract for JLAB solenoid work - Josh
  • Make movie file out of jt - Mike Beizer

Minutes from previous

  • Long pants will be worn in Hall D at all times until further notice.

New Action Items

    • In attendance W. Crahen, C. Hutton, V. Razmyslovich, J. Lagner, R. Getz, W. Sachleben, Tim Whitlatch, J. Conger, S. Mcarthy, G. Biallas, T Carstens, B. Bunton, M. Stevens, S. Speigel, J. Thomason, J. Foyles, C. Heck, T. Mann, M. Beizer, A. Johnson, J. Ballard, M. Bear, A. Sitnikov, D. Butler, M. Devendorf