Difference between revisions of "October 25, 2019 FCAL Insert Design Meeting"

From GlueXWiki
Jump to: navigation, search
(Minutes and Action Items)
(Minutes and Action Items)
Line 29: Line 29:
 
** No Survey needed for 12 crystal tests (initially)
 
** No Survey needed for 12 crystal tests (initially)
 
** Need vertical adjustment capability
 
** Need vertical adjustment capability
** Ste
+
* Need to ask Matt Shepherd for measurements of previous FCAL lead glass modules
 +
* Keith presented a fairly detailed assembly sequence and plan

Revision as of 16:19, 9 December 2019

Meeting Time and Place =

Wednesday Oct, 9 10:00 am At Jefferson Lab, room TED 2504

  • Present - Sasha Somov, Josh Crafts, Eugene, Stephanie, Keith Harding, Tim, Fernando, Chris Stanislav

Agenda

Minutes and Action Items

  • Josh has 1mm fiber for test
  • Mu metal shields are in house - 6mm shorter than steel
  • 12 crystal test setup
    • No Survey needed for 12 crystal tests (initially)
    • Need vertical adjustment capability
  • Need to ask Matt Shepherd for measurements of previous FCAL lead glass modules
  • Keith presented a fairly detailed assembly sequence and plan