Line 17: Line 17:
 
* Cooling of blocks - 2.1 KW needed
 
* Cooling of blocks - 2.1 KW needed
 
* Support structure and assy sequence  
 
* Support structure and assy sequence  
** [[Media:Module installation procedure.pdf]]
+
** [[Media:FCAL Insert Module installation procedure.pdf]]
 
* electronics patch panels DS of crystal pmts
 
* electronics patch panels DS of crystal pmts
 
* Discuss Testing of soldered assembly and mag field testing
 
* Discuss Testing of soldered assembly and mag field testing

Revision as of 16:22, 9 December 2019

Meeting Time and Place =

Wednesday Oct, 9 10:00 am At Jefferson Lab, room TED 2504

  • Present - Sasha Somov, Josh Crafts, Eugene, Stephanie, Keith Harding, Tim, Fernando, Chris Stanislav

Agenda

Minutes and Action Items

  • Josh has 1mm fiber for test
  • Mu metal shields are in house - 6mm shorter than steel
  • 12 crystal test setup
    • No Survey needed for 12 crystal tests (initially)
    • Need vertical adjustment capability
  • Need to ask Matt Shepherd for measurements of previous FCAL lead glass modules
  • Keith presented a fairly detailed assembly sequence and plan