==Needed for CD-3 May 2008==
 
==Needed for CD-3 May 2008==
  
* Full trigger functional design
+
* Full trigger/timing functional design including energy sum trigger and timing distribution
* Full DAQ functional design
+
* Full DAQ functional design including trigger distribution
* Functional (80%) design for all DAQ and trigger hardware (component choice and circuit layouts not required)
+
* Functional (i.e. 80%) design for all trigger and DAQ hardware.  N.B. circuit layouts and component choice not required.
 
** front-end timing distribution
 
** front-end timing distribution
 
** trigger creation and distribution
 
** trigger creation and distribution
 +
** TI card
 +
** TS board
 +
* Prototype of major CODA components, ROC, EMU, ER plus run control
 +
* Choice of controls framework and basic implementation plan
  
  

Revision as of 15:09, 3 December 2007

Needed for CD-3 May 2008

  • Full trigger/timing functional design including energy sum trigger and timing distribution
  • Full DAQ functional design including trigger distribution
  • Functional (i.e. 80%) design for all trigger and DAQ hardware. N.B. circuit layouts and component choice not required.
    • front-end timing distribution
    • trigger creation and distribution
    • TI card
    • TS board
  • Prototype of major CODA components, ROC, EMU, ER plus run control
  • Choice of controls framework and basic implementation plan


DAQ Milestones

The full DAQ (approximately 80 full crates) must be ready for testing the complete detector with cosmic or pulser triggers by 1Q FY 2014. First beam to the hall is expected in 4Q FY 2014, with low-rate production data taking expected to start in 4Q FY 2015. High-rate production data taking may start as early as 4Q FY 2016, assuming funds are available to upgrade the detector.


DAQ Development/Demonstration Milestones

2006

  • Production event transfer system - done Aug 2006
  • Procuction event i/o package - done Aug 2006

2007

  • DAQ test farm by 28-Sep-2007, PED deliverable - done Jan 2007
  • Prototype software component framework - done Jun 2007
  • Prototype run control system - done Jun 2007
  • Production inter-process communication package - done Nov 2007
  • Prototype front-end driver software (almost done)

2008

  • Prototype staged/parallel event builder by Apr 2008, PED deliverable
  • Prototype single crate timing and trigger distribution by Jun 2008
  • Preliminary complete trigger design by Jun 2008
  • Prototype remaining software components by Jun 2008
  • Simulation of full system at low rate (run control, ET, multiple EB's, ER, etc) by Oct 2008
  • Prototype L3 farm management software by Oct 2008
  • Develop CODA-based electronics test stands by Oct 2008

2009

  • Prototype multi-crate timing and trigger distribution by Oct 2009
  • Demonstate single-crate high-speed readout by Oct 2009
  • Complete trigger design by Oct 2009

2010

  • Demonstrate multi-crate high-speed readout by Oct 2010

2011

  • Simulation of full system at high rate by 2011.
  • Production front-end driver software by 2011.
  • Production trigger and timing distribution by 2011.
  • Production experiment control system by 2011.
  • Production component framework by 2011.
  • Production software components by 2011.


DAQ Detector Needs

DAQ systems of various sorts will be needed during detector development, construction, and checkout. Below, "parallel" means that parallel or staged event building is needed. "Small" means four crates or less, and "large" means more than four crates. In general, parallel readout is only needed at very high rates, where a single network connection cannot handle all the data.

  • Single-crate DAQ systems are needed now (Jul-2007).
  • Small systems will be needed by Oct 2008.
  • Single-crate with trigger/timing needed for FCAL test Summer 2008
  • Large systems will be needed by Oct 2010.
  • Parallel, large systems will be needed by Oct 2011.

In all cases the readout crates may be full.

(Elton suggests creating a table of configurations needed...ejw, 14-Aug-2007)


Online/Controls Milestones