Online Major Milestones

From GlueXWiki
Revision as of 14:09, 27 August 2007 by Wolin (Talk | contribs)

Jump to: navigation, search

DAQ Milestones

The full DAQ (approximately 80 full crates) must be ready for testing the complete detector with cosmic or pulser triggers by 1Q FY 2014. First beam to the hall is expected in 4Q FY 2014, with low-rate production data taking expected to start in 4Q FY 2015. High-rate production data taking may start as early as 4Q FY 2016, assuming funds are available to upgrade the detector.


DAQ Development/Demonstration Milestones

  • Production event transfer system (done, Aug 2006)
  • Procuction event i/o package (done, Aug 2006)
  • Production inter-process communication package (expect done Sep 2007)
  • Prototype software component framework (done, Jun 2007)
  • Prototype run control system (done, Jun 2007)
  • Prototype front-end driver software (almost done)
  • DAQ test farm by 28-Sep-2007 (PED deliverable, done, Jan 2007)
  • Prototype staged/parallel event builder by Apr 2008 (PED deliverable)
  • Prototype single crate timing and trigger distribution by Jun 2008
  • Prototype remaining software components by Jun 2008
  • Simulation of full system at low rate (run control, ET, multiple EB's, ER, etc) by Oct 2008
  • Prototype L3 farm management software by Oct 2008
  • Prototype multi-crate timing and trigger distribution by Oct 2009
  • Demonstate single-crate high-speed readout by Oct 2009
  • Demonstrate multi-crate high-speed readout by Oct 2010
  • Simulation of full system at high rate by 2011.
  • Production front-end driver software by 2011.
  • Production trigger and timing distribution by 2011.
  • Production experiment control system by 2011.
  • Production component framework by 2011.
  • Production software components by 2011.


DAQ Detector Needs

DAQ systems of various sorts will be needed during detector development, construction, and checkout. Below, "parallel" means that parallel or staged event building is needed. "Small" means four crates or less, and "large" means more than four crates. In general, parallel readout is only needed at very high rates, where a single network connection cannot handle all the data.

  • Single-crate DAQ systems are needed now (Jul-2007).
  • Small systems will be needed by Oct 2008.
  • Single-crate with trigger/timing needed for FCAL test in Oct 2008
  • Large systems will be needed by Oct 2010.
  • Parallel, large systems will be needed by Oct 2011.

In all cases the readout crates may be full.

(Elton suggests creating a table of configurations needed...ejw, 14-Aug-2007)


Online/Controls Milestones