Needed for Subsystem Review May 2008 and for CD-3 Review Summer 2008

  • Revisit and verify energy-sum algorithm with latest hardware design, etc.
  • Functional design of overall timing distribution system.
  • Functional design of energy-sum trigger.
  • Functional design of overall trigger distribution system.
  • Functional design of full DAQ.
  • Electronics functional block design including full block specification for all trigger and DAQ hardware, suitable to be sent off to industry for component choice, layout, and fabrication. Prototypes/testing only needed to demonstrate proof-of-principle of speculative ideas.
    • timing distribution system.
    • energy-sum boards.
    • TI board.
    • TS board.
  • Preliminary libraries for reading out existing custom boards (F1TDC, FADC, etc).
  • Prototypes of major CODA 3 components: ROC, EMU, ER, and run control.
    • n.b. already have cMsg, ET, EVIO, etc.
  • Understanding of event size, backplane and network bandwidth requirements, etc.
  • Demonstrate 200 kHz triggering and high-speed (2E CBT) readout in single crate.
  • Choice of controls framework and basic implementation plan.


DAQ Milestones

The full DAQ (approximately 80 full crates) must be ready for testing the complete detector with cosmic or pulser triggers by 1Q FY 2014. First beam to the hall is expected in 4Q FY 2014, with low-rate production data taking expected to start in 4Q FY 2015. High-rate production data taking may start as early as 4Q FY 2016, assuming funds are available to upgrade the detector.


DAQ Development/Demonstration Milestones

2006

  • Production event transfer system - done Aug 2006
  • Procuction event i/o package - done Aug 2006

2007

  • DAQ test farm by 28-Sep-2007 (PED deliverable) - done Jan 2007
  • Prototype software component framework - done Jun 2007
  • Prototype run control system - done Jun 2007
  • Production event transfer system - done Jun 2007
  • Production inter-process communication package - done Nov 2007

2008 (see also subsystem and CD-3 review milestones above)

  • Develop CODA-based electronics test stand by Jul 2008
  • Preliminary energy-sum trigger design by Sep 2008 (PED deliverable)
  • Prototype staged/parallel event builder by Sep 2008 (PED deliverable)
  • Prototype single crate timing and trigger distribution by Nov 2008
  • Simulation of full system at low rate (run control, ET, multiple EB's, ER, etc) by Nov 2008
  • Prototype L3 farm management software by Nov 2008
  • Prototype TI board by Nov 2008
  • Prototype energy-sum boards by Nov 2008
  • Demonstrate 200 kHz staged parallel event building by Nov 2008
  • Demonstrate 200 kHz block event readout and transfer by Nov 2008

2009

  • Master trigger design by Aug 2009 (PED deliverable)
  • Prototype multi-crate timing and trigger distribution by Oct 2009
  • Complete trigger design by Oct 2009
  • Prototype TS board by Oct 2009

2010

  • Demonstrate multi-crate high-speed readout
  • Simulation of full system at high rate
  • Production front-end driver software
  • Production trigger and timing distribution
  • Production experiment control system
  • Production component framework
  • Production software components
  • Production TI board
  • Production TS board
  • Production energy-sum boards

2011


DAQ Detector Needs

DAQ systems of various sorts will be needed during detector development, construction, and checkout. Below, "parallel" means that parallel or staged event building is needed. "Small" means four crates or less, and "large" means more than four crates. In general, parallel readout is only needed at very high rates, where a single network connection cannot handle all the data.

  • Single-crate DAQ systems are needed now (Jul-2007).
  • Small systems will be needed by Oct 2008.
  • Single-crate with trigger/timing needed for FCAL test Summer 2008
  • Large systems will be needed by Oct 2010.
  • Parallel, large systems will be needed by Oct 2011.

In all cases the readout crates may be full.

(Elton suggests creating a table of configurations needed...ejw, 14-Aug-2007)


Online/Controls Milestones

2007

  • Choose inter-process communication package - done Jan 2007
  • Choose event I/O package - done Jan 2007

2008

  • Choose controls framework by May 2008
  • Design monitoring system by Jul 2008 (PED deliverable)
  • Design alarm system by Sep 2008 (PED deliverable)
  • Design experiment control system by Sep 2008 (PED deliverable)

2009

  • Design event display by Mar 2009 (PED deliverable)

2010

2011