Online Major Milestones

From GlueXWiki
Revision as of 17:47, 18 January 2008 by Wolin (Talk | contribs)

Jump to: navigation, search

Purpose

Below we outline our strategy to develop an online system that meets the design goals listed in Online_Design_Goals and Elton's Hall D Design Goal document (GlueX-doc-866 in the DocDB). Here we only list major milestones along this development path. Detailed milestones and assignment of names can be found in Elke's Action Item Tracker and other documents. As decided in the 14-Dec-2008 OWG meeting, electronics milestones are also included here.

Basic Considerations

The complete DAQ (approximately 80 full crates) must be ready for commissioning the complete detector with cosmic or pulser triggers by 1Q FY 2014. First beam to the hall is expected in 4Q FY 2014, with low-rate production data taking expected to start in 4Q FY 2015. High-rate production data taking may start as early as 4Q FY 2016, assuming funds are available to upgrade the detector. Beneficial occupancy of Hall D is expected in summer 2010, counting house in fall 2011. Trigger, DAQ, monitoring, and control systems will be needed starting in early 2011 to check out detector subsystems as they are being installed and commissioned.

Note that the 12 GeV project specifies a beam rate of 10**7 photons/sec, but that we plan an eventual upgrade to 10**8. All components must be designed to be capable of, or upgradable or expandable to, 10**8 running.


Needed for Subsystem Review May 2008 and for CD-3 Review Summer 2008

N.B. All designs must satisfy the design goals described in Online_Design_Goals.

  • Overall trigger diagram - Feb 2008.
  • Interface document from Electronics group defining clock distribution system and energy-sum trigger - Feb 2008.
  • Interface document from DAQ group defining trigger distribution system and CODA 3 major components and functionality - Feb 2008.
  • Conceptual design of DAQ system specifying strategy to integrate devices and software described in the above two documents into a working system - Mar 2008.
  • Preliminary libraries for reading out existing custom boards (F1TDC, FADC) - Apr 2008.
  • Demonstrate crate-sum trigger components operating at 250 MHz - Apr 2008.
  • Demonstrate 200 kHz triggering and high-speed readout (> 100 MB/s) of multiple FADC/F1TDC modules in a single crate - Apr 2008.
  • Choice of controls framework - Apr 2008.
  • Interface document with Computer Center defining networking strategy, how to move data from counting house to storage silo, etc. - Apr 2008.


Notes:

  • An "interface document" defines major system components and their functionality, as well as fundamental agreements between two parties.
  • A "circuit specification" describes circuits at a level such that an electronics design firm could produce the devices. E.g. I/O signal levels and circuit functionality are described in detail, but IC choice is not specified.


Trigger/DAQ Milestones

2006

  • Production event transfer system - done Aug 2006
  • Production event I/O package - done Aug 2006

2007

  • DAQ test farm by 28-Sep-2007 (PED deliverable) - done Jan 2007
  • Prototype software component framework - done Jun 2007
  • Prototype run control system - done Jun 2007
  • Production inter-process communication package - done Nov 2007

2008

  • Subsystem review May 2008 and CD-3 review July 2008, see milestones above
  • Develop CODA-based electronics test stand by Jul 2008
  • Preliminary energy-sum and master trigger design by Sep 2008 (PED deliverable)
  • Prototype staged/parallel event builder by Sep 2008 (PED deliverable)
  • Revisit energy-sum trigger algorithm using latest hardware design - Nov 2008.
  • Verify event size and resulting backplane and network bandwidth requirements - Nov 2008.
  • Prototype single crate timing and trigger distribution by Nov 2008
  • Simulation of full system at low rate (run control, ET, multiple EB's, ER, etc) by Nov 2008
  • Prototype TI board by Nov 2008
  • Prototype energy-sum and master trigger boards by Nov 2008
  • Demonstrate 200 kHz staged parallel event building by Nov 2008
  • Demonstrate 200 kHz block event readout and transfer by Nov 2008
  • Prototypes of major CODA 3 components, including readout controller, staged/parallel event builder, event recorder, and run control system by Nov 2008.
  • Interface document with Accelerator division defining strategy for hall/accelerator inter-operation by Nov 2008.
  • Circuit specifications for clock distribution system - Nov 2008.
  • Circuit specifications energy sum trigger system - Nov 2008.
  • Circuit specifications for trigger distribution system - Nov 2008.

2009

  • Prototype L3 farm management software by Sep 2009
  • Master trigger design by Aug 2009 (PED deliverable)
  • Prototype multi-crate timing and trigger distribution by Oct 2009
  • Overall trigger design by Oct 2009
  • Prototype TS board by Oct 2009

2010

  • Demonstrate multi-crate high-speed readout
  • Simulation of full system at high rate
  • Production front-end driver software
  • Production timing distribution system
  • Production trigger distribution system
  • Production experiment control system
  • Production component framework
  • Production software components
  • Production TI board
  • Production TS board
  • Production energy-sum and master trigger boards

2011

  • Integration and test of all final Trigger/DAQ system components by Sep 2011
  • Install trigger and DAQ in Hall D as electronics and detector components begin to arrive

2012

  • Trigger/DAQ ready for testing hardware being installed in Hall D


Trigger/DAQ Detector Needs

DAQ systems of various sorts will be needed during detector development, construction, and checkout. Below, "parallel" means that parallel or staged event building is needed. "Small" means four crates or less, and "large" means more than four crates. In general, parallel readout is only needed at very high rates, where a single network connection cannot handle all the data.

  • Single-crate DAQ systems are needed now (Jul-2007).
  • Small systems will be needed by Oct 2008.
  • Single-crate with trigger/timing needed for FCAL test Summer 2008
  • Large systems will be needed by Oct 2010.
  • Parallel, large systems will be needed by Oct 2011.

In all cases the readout crates may be full.

(Elton suggests creating a table of configurations needed...ejw, 14-Aug-2007)


Monitoring/Controls Milestones

2007

  • Choose inter-process communication package - done Jan 2007

2008

  • Choose controls framework by May 2008
  • Design monitoring system by Jul 2008 (PED deliverable)
  • Design alarm system by Sep 2008 (PED deliverable)
  • Design experiment control system by Sep 2008 (PED deliverable)
  • Choose request tracking system by Nov 2008
  • Choose code management framework by Nov 2008 (in conjunction with offline)
  • Choose build framework by Nov 2008 (in conjunction with offline)


2009

  • Design event display by Mar 2009 (PED deliverable)

2010

2011

  • Install monitoring and controls systems in preparation for hardware installation in Hall D

2012

  • Monitoring/controls ready for testing hardware being installed in Hall D


Electronics Milestones

  • Fernando will fill this in...