(in preparation...ejw, aug-2007)
 
(in preparation...ejw, aug-2007)
  
 +
==Needed for Subsystem Review May 2008 and for CD-3 Review Summer 2008==
 +
 +
* Revisit and verify energy-sum algorithm with latest hardware design, etc.
 +
** Eugene working on event simulation
 +
** Chinese group will work on algorithm with Dave D's help
 +
** David L will help with offline software
 +
** Elliott will kibbitz
 +
* Functional design of overall timing distribution system.
 +
** Chris, Ed, Fernando
 +
* Functional design of energy-sum trigger.
 +
** Dave D, Chris, Fernando
 +
* Functional design of overall trigger distribution system.
 +
** Ed, Chris, Dave A, Fernando
 +
* Functional design of full DAQ.
 +
** Graham, Dave A, Elliott
 +
* Electronics functional block design including full block specification for all trigger and DAQ hardware, suitable to be sent off to industry for component choice, layout, and fabrication.  Prototypes/testing only needed to demonstrate proof-of-principle of speculative ideas.
 +
** timing distribution system.
 +
*** Chris, Ed
 +
** energy-sum boards.
 +
*** Dave D, Chris
 +
** TI board.
 +
*** Ed, Dave A
 +
** TS board.
 +
*** Ed, Dave A
 +
* Preliminary libraries for reading out existing custom boards (F1TDC, FADC, etc).
 +
** Dave A
 +
* Prototypes of major CODA 3 components: ROC, EMU, ER, and run control.
 +
** Graham, Dave A, Vardan, Carl, Elliott
 +
** n.b. already have cMsg, ET, EVIO, etc.
 +
* Understanding of event size, backplane and network bandwidth requirements, etc.
 +
** Eugene, David L, Fernando, Elliott
 +
* Demonstrate 200 kHz triggering and high-speed (1E CBT? 2E CBT?) readout in single crate.
 +
** Dave A, Ed
 +
* Choice of controls framework and basic implementation plan.
 +
** Elliott
 +
 +
 +
==Overall Work Breakdown==
  
 
* L1 Trigger
 
* L1 Trigger

Revision as of 16:33, 6 December 2007

(in preparation...ejw, aug-2007)

Needed for Subsystem Review May 2008 and for CD-3 Review Summer 2008

  • Revisit and verify energy-sum algorithm with latest hardware design, etc.
    • Eugene working on event simulation
    • Chinese group will work on algorithm with Dave D's help
    • David L will help with offline software
    • Elliott will kibbitz
  • Functional design of overall timing distribution system.
    • Chris, Ed, Fernando
  • Functional design of energy-sum trigger.
    • Dave D, Chris, Fernando
  • Functional design of overall trigger distribution system.
    • Ed, Chris, Dave A, Fernando
  • Functional design of full DAQ.
    • Graham, Dave A, Elliott
  • Electronics functional block design including full block specification for all trigger and DAQ hardware, suitable to be sent off to industry for component choice, layout, and fabrication. Prototypes/testing only needed to demonstrate proof-of-principle of speculative ideas.
    • timing distribution system.
      • Chris, Ed
    • energy-sum boards.
      • Dave D, Chris
    • TI board.
      • Ed, Dave A
    • TS board.
      • Ed, Dave A
  • Preliminary libraries for reading out existing custom boards (F1TDC, FADC, etc).
    • Dave A
  • Prototypes of major CODA 3 components: ROC, EMU, ER, and run control.
    • Graham, Dave A, Vardan, Carl, Elliott
    • n.b. already have cMsg, ET, EVIO, etc.
  • Understanding of event size, backplane and network bandwidth requirements, etc.
    • Eugene, David L, Fernando, Elliott
  • Demonstrate 200 kHz triggering and high-speed (1E CBT? 2E CBT?) readout in single crate.
    • Dave A, Ed
  • Choice of controls framework and basic implementation plan.
    • Elliott


Overall Work Breakdown

  • L1 Trigger
    • Trigger hardware and cabling
    • Trigger programming
  • Trigger/timing distribution
    • Trigger distribution hardware and cabling
    • Timing distribution hardware and cabling
  • Readout electronics
    • Crates
    • Crate monitoring
    • Modules
    • Detector cabling, esp. final two feet
    • Module programming
  • Event building
    • Event builder hardware and network configuration
    • Event builder programming
    • Sync and other special events
    • ET system configuration
  • L3 trigger
    • L3 farm hardware and networks
    • ET system configuration
    • Event distribution system
    • Farm management software
  • Event storage
    • Raid hardware
    • Hardware connection to silo
    • File transfer software
  • Experiment and slow controls
  • Event monitoring/display
    • Online event display
    • Online event monitoring, display of results, alarm system
  • Electronic record keeping
    • Electronic logbook
    • Run database hardware and configuration
    • Software to enter data in to run database
  • Computers, networks, telecom
    • Computers for hall and counting house
      • UPS, distribution panel, wiring
    • Network in hall and counting house
      • Switches
      • Cabling
    • Telecom in hall and counting house
      • Distribution panels
      • Cabling
      • Phones, installation
  • Counting house physical environment
    • Furniture


Notes

  • Cabling has to be carefully planned and coordinated among a number of groups to ensure maintenance is simple