Difference between revisions of "Online Work Breakdown"

From GlueXWiki
Jump to: navigation, search
m
m
 
(One intermediate revision by the same user not shown)
Line 1: Line 1:
 
This document is continuously in preparation...ejw, Aug 2007
 
This document is continuously in preparation...ejw, Aug 2007
 
 
==Needed for Subsystem Review May 2008 and for CD-3 Review Summer 2008==
 
 
* Revisit and verify energy-sum algorithm with latest hardware design, etc.
 
** Eugene working on event simulation
 
** Chinese group will work on algorithm with Dave D's help
 
** David L will help with offline software
 
** Dave D will consult, Elliott will kibbutz
 
* Functional design of overall timing distribution system.
 
** Chris, Ed, Fernando
 
* Functional design of energy-sum trigger.
 
** Dave D, Chris, Fernando
 
* Functional design of overall trigger distribution system.
 
** Ed, Chris, Dave A, Fernando
 
* Functional design of full DAQ.
 
** Graham, Dave A, Elliott
 
* Electronics functional block design including full block specification for all trigger and DAQ hardware, suitable to be sent off to industry for component choice, layout, and fabrication.  Prototypes/testing only needed to demonstrate proof-of-principle of speculative ideas.
 
** timing distribution system.
 
*** Chris, Ed
 
** energy-sum boards.
 
*** Dave D, Chris
 
** TI board.
 
*** Ed, Dave A
 
** TS board.
 
*** Ed, Dave A
 
* Preliminary libraries for reading out existing custom boards (F1TDC, FADC, etc).
 
** Dave A
 
* Prototypes of major CODA 3 components: ROC, EMU, ER, and run control.
 
** Graham, Dave A, Vardan, Carl, Elliott
 
** n.b. already have cMsg, ET, EVIO, etc.
 
* Understanding of event size, backplane and network bandwidth requirements, etc.
 
** Eugene, David L, Fernando, Elliott
 
* Demonstrate 200 kHz triggering and high-speed (1E CBT? 2E CBT?) readout in single crate.
 
** Dave A, Ed
 
* Choice of controls framework and basic implementation plan.
 
** Elliott
 
 
  
 
==Overall Work Breakdown==
 
==Overall Work Breakdown==

Latest revision as of 12:12, 28 February 2008

This document is continuously in preparation...ejw, Aug 2007

Overall Work Breakdown

  • L1 Trigger
    • Trigger hardware and cabling
    • Trigger programming
  • Trigger/timing distribution
    • Trigger distribution hardware and cabling
    • Timing distribution hardware and cabling
  • Readout electronics
    • Crates
    • Crate monitoring
    • Modules
    • Detector cabling, esp. final two feet
    • Module programming
  • Event building
    • Event builder hardware and network configuration
    • Event builder programming
    • Sync and other special events
    • ET system configuration
  • L3 trigger
    • L3 farm hardware and networks
    • ET system configuration
    • Event distribution system
    • Farm management software
  • Event storage
    • Raid hardware
    • Hardware connection to silo
    • File transfer software
  • Experiment and slow controls
  • Event monitoring/display
    • Online event display
    • Online event monitoring, display of results, alarm system
  • Electronic record keeping
    • Electronic logbook
    • Run database hardware and configuration
    • Software to enter data in to run database
  • Computers, networks, telecom
    • Computers for hall and counting house
      • UPS, distribution panel, wiring
    • Network in hall and counting house
      • Switches
      • Cabling
    • Telecom in hall and counting house
      • Distribution panels
      • Cabling
      • Phones, installation
  • Counting house physical environment
    • Furniture


Notes

  • Cabling has to be carefully planned and coordinated among a number of groups to ensure maintenance is simple