Overall trigger timing

From GlueXWiki
Revision as of 10:23, 21 July 2006 by Zisis (Talk | contribs)

Jump to: navigation, search

Timing Scheme

From Elliott: Below is my current understanding of the trigger timing for the BCAL test:


Time
What
Comment
0 ns
electron hits tagger foil

115 ns
photon hits BCAL
125 ns to alcove, but BCAL is about 10 feet upstream on the platform
215 ns
BCAL PMT signals reach discriminators
20 ns in PMT plus 80 ns cable
245 ns
discriminator sum outputs available
30 ns a guess, but must be delayed before final AND in any case
310 ns
Tagger MOR reaches final AND logic
230 ns + 80 ns? cable, see Tagger trigger timing
310 ns
discriminator sums reach final AND
Delayed to match MOR
325 ns
result of final AND reaches trigger supervisor
15 ns a guess through trigger logic
370 ns
trigger supervisor L1 accept ready
45 ns internal to TS
385 ns
gate reaches ADC crate
15 ns a guess, cable plus gate generator plus cable
385 ns
BCAL signals reach ADC crate
20 ns in PMT plus 250 ns cable plus photon flight time



Note that my calculation shows the ADC gate reaching the crate EXACTLY at the same time as the signals. This is not a good situation as any slip in timing cuts off the ADC. But also note that the 80 ns cable from the CLAS area to our crates is also a guess, perhaps 60 ns is correct. Even so this only gives us 20 ns to play with.

Thus I tentatively conclude the current cabling will NOT work.

Two solutions are possible: shorten the MOR delay, or add delay to the ADC signals. The former is far preferable as it only involves one cable, whereas the latter involves 36 cables. But it is not clear how much we can shorten the MOR via a direct fast cable between the tagger and the BCAL trigger crates.

I propose we proceed on the former. If the latter becomes necessary there are a few possibilities, including purchase of cables, cutting some of the unused 170 ns in half and installing new ends to give 80 ns delay cables, etc.

Comments are welcome...

Comments

I agree that this will not work. I also agree on the plan of action, in the following priority: 1) Try to shorten MOR, 2) Cut unused 70ns cable (if there are enough and if this is ok with folks like Richard) and 3) Purchase new cables. -- Zisis