Photon Beam Commissioning Discussion July 7, 2014
From GlueXWiki
Contents
Organization
- Time: 4 pm EST
- Connecting: detailed instructions are here
- H.323 ip address: 199.48.152.152
- web browser: https://bluejeans.com/536076821
- phone: 408-740-7256 or 888-240-2560
- Conference id: 536076821
References
Agenda
- Announcements
- Electron Commissioning (Todd/Mike)
- Photon Commissioning Draft (Eugene)
- Goals for Aug 8 Review
- Other business
Minutes
- Attending: Elton, Eugene, Alexandre, Sasha (Hall D); Mike McCaughan, Todd Satogata (Accelerator); Richard (UConn); Curtis (CMU).
- Announcements
- Electron Commissioning (Todd/Mike)
- Mike detailing procedures for commissioning electron beam based on experience in April
- Much learned from beam delivery
- Confidence that delivery this fall will be clearner
- Expect: days to tune after spinning up to 5.5 pass; reasonable radiation without radiator
- Initial goal for emittance is 20 nm*rad x 2. [Design is 25 nm*rad in x and 10 nm*rad in y]
- Setup beam so that virtual focus of electron beam is at the collimator
- Need to characterize the ion chambers (minimizing scrapping and tails)
- nAmp bpms should be installed, but operation is not needed for commissioning
- Fast feedback is also not critical
- Simulation of beam environment
- Richard will provide a geometry for Todd to run simulations
- Richard will include the mapped tagger magnetic field
- Todd will provide a magnetic field for the quad immediately upstream of the tagger magnet.
- (Eugene) Suggest to have the quad off during initial commissioning.
- Radiators
- Production radiators are (10^-5, 3x10^-4, 10^-3)
- Propose the following set for commissioning: (3x10^-5, 10^-4, 3x10^-4)
- Mike detailing procedures for commissioning electron beam based on experience in April
- Photon Commissioning Draft (Eugene)
- Discussion of draft plan submitted as homework to ERR
- Goals for Aug 8 Review
- Other business