Difference between revisions of "Photon Beam Commissioning Discussion Oct 15, 2014"

From GlueXWiki
Jump to: navigation, search
(Minutes)
Line 31: Line 31:
  
 
# Announcements
 
# Announcements
#* Accelerator Schedule:  
+
#* Accelerator Schedule: Weekend: beam to dumplet, Monday morning: lock up Hall D/tagger, evening tune beam to dump, Tuesday: CW to tagger dump, Wed morning: insert radiator
 
# ARR3 Recommendations
 
# ARR3 Recommendations
 
#* All recommendations complete and request for operation has been sent to Patrizia
 
#* All recommendations complete and request for operation has been sent to Patrizia
 +
#* Final documentation on the completion of items needed for Javier.
 +
#* RadCon will tag the completed shielding in the tagger area with a plaque. The completion will be confirmed to Eugene
 +
#* Fanning has sent a confirmation of all safety items checked during the walkthrough last Thursday
 
# Accelerator and Hall D Interface Document - update
 
# Accelerator and Hall D Interface Document - update
 
# Update on Photon Commissioning (Alexandre)
 
# Update on Photon Commissioning (Alexandre)
 +
#* small changes to the plan are being implemented including the last links
 +
#* Tentative proposal to start shifts: standby shifts on Tue evening/night, start regular shifts on Wed day shift
 +
#* Need to take baseline rates of profile monitor before commissioning starts. Hovanes will do this.
 +
#* Eugene: Need checklists before starting various plans. Alexandre: There are checklists for the electron beam and photon beam separately
 
# [[Beam Simulations]]
 
# [[Beam Simulations]]
 
# RadCon update
 
# RadCon update
 +
#* Note: shielding is being added to the gap in the wall nearest to the dump by Tom's crew
 
#* Checklists
 
#* Checklists
 
# Other business
 
# Other business

Revision as of 17:05, 15 October 2014

Organization

  • Time: 4:00 pm EST
  • Connecting: detailed instructions are here
  • Conference id: 536076821

References

Action Items

  • Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Eugene, Alexandre for Hall D)
    • Need rates for profiler, start counter, ps
  • Complete the tagger drawing with the expected configuration for the fall running, including all shielding. (Tim, Chuck, Elton)

Agenda

  1. Announcements
  2. ARR3 Recommendations
    • All recommendations complete and request for operation has been sent to Patrizia
  3. Accelerator and Hall D Interface Document - update
  4. Update on Photon Commissioning (Alexandre)
  5. Beam Simulations
  6. RadCon update
    • Checklists
  7. Other business

Minutes

"Attending: Elton, Beni, Alexandre, Hovanes, Eugene (Hall D); Todd (CASA); Pavel (RadCon); Curtis (CMU); Richard (UConn).

  1. Announcements
    • Accelerator Schedule: Weekend: beam to dumplet, Monday morning: lock up Hall D/tagger, evening tune beam to dump, Tuesday: CW to tagger dump, Wed morning: insert radiator
  2. ARR3 Recommendations
    • All recommendations complete and request for operation has been sent to Patrizia
    • Final documentation on the completion of items needed for Javier.
    • RadCon will tag the completed shielding in the tagger area with a plaque. The completion will be confirmed to Eugene
    • Fanning has sent a confirmation of all safety items checked during the walkthrough last Thursday
  3. Accelerator and Hall D Interface Document - update
  4. Update on Photon Commissioning (Alexandre)
    • small changes to the plan are being implemented including the last links
    • Tentative proposal to start shifts: standby shifts on Tue evening/night, start regular shifts on Wed day shift
    • Need to take baseline rates of profile monitor before commissioning starts. Hovanes will do this.
    • Eugene: Need checklists before starting various plans. Alexandre: There are checklists for the electron beam and photon beam separately
  5. Beam Simulations
  6. RadCon update
    • Note: shielding is being added to the gap in the wall nearest to the dump by Tom's crew
    • Checklists
  7. Other business