Photon Beam Commissioning Discussion Oct 15, 2014

From GlueXWiki
Revision as of 17:11, 8 October 2014 by Elton (Talk | contribs) (Action Items)

Jump to: navigation, search

Organization

  • Time: 4:00 pm EST
  • Connecting: detailed instructions are here
  • Conference id: 536076821

References

Action Items

  • Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Eugene, Alexandre for Hall D)
    • Need rates for profiler, start counter, ps
  • Complete the tagger drawing with the expected configuration for the fall running, including all shielding. (Tim, Chuck, Elton)

Agenda

  1. Announcements
  2. ARR3 Recommendations
  3. Accelerator and Hall D Interface Document - update
  4. Update on Photon Commissioning (Alexandre)
  5. Beam Simulations
  6. RadCon update
  7. Other business

Minutes

"Attending: