Difference between revisions of "Photon Beam Polarimetry"

From GlueXWiki
Jump to: navigation, search
Line 3: Line 3:
  
 
== Expected Timeline ==
 
== Expected Timeline ==
* February 2 - 5: (?) Kei visits ASU
+
* February 2 - 5 (?): Kei visits ASU
* mid-February ship: triplet to JLab  
+
* mid-February: ship triplet to JLab  
 
* First week after delivery: Survey by JLab
 
* First week after delivery: Survey by JLab
 
* February 16 - March 27: installation
 
* February 16 - March 27: installation
Line 12: Line 12:
 
== Hardware Division ==
 
== Hardware Division ==
 
* ASU
 
* ASU
** motor
+
** motor ([ftp://ftp.phytron.de/phytron-usa/stepper_motors/vacuum-us.pdf data sheet])
** HV supply
+
** controller
 +
** power supply
 +
**# 4 channels of +12V, 0.21 amps per channel
 +
**# 4 channels of -12V, 0.21 amps per channel
 +
**# 1 channel of +200V, the leakage current on the silicon strip detecter is 3.3 micro-amps
 +
** 32 short SSI cables with Lemo
 +
** vacuum rated limit switches ([http://www.public.asu.edu/~dugger/363-SWITCH-DS.pdf data sheet])
 
* JLab
 
* JLab
** cables
+
** fADCs
 +
**# 2 fADC250s on PSC VXS crate
 +
** 32 coax cables with Lemos on both ends (Fernando). Require 55ft to racks
 +
** turbo vacuum pump (Tim)
  
 
== Things to do at ASU ==
 
== Things to do at ASU ==
 
* packaging, shipping
 
* packaging, shipping
 +
* testing(?)
  
 
== Things to do at JLab ==
 
== Things to do at JLab ==
* preparation of cables
+
* preparation of hardware before shipment
 
* installation
 
* installation
 +
* testing with source(?)
  
 
== Management/Safety ==
 
== Management/Safety ==

Revision as of 13:11, 8 January 2015

This page contains a list of to do items for installing the triplet polarimeter for the Spring 2015 GlueX run. Items that used to be on this page are now at the bottom in Items From Before January 2015

Expected Timeline

  • February 2 - 5 (?): Kei visits ASU
  • mid-February: ship triplet to JLab
  • First week after delivery: Survey by JLab
  • February 16 - March 27: installation
  • March 28 - April 2: testing
  • April 3 - May 4: physics beam

Hardware Division

  • ASU
    • motor (data sheet)
    • controller
    • power supply
      1. 4 channels of +12V, 0.21 amps per channel
      2. 4 channels of -12V, 0.21 amps per channel
      3. 1 channel of +200V, the leakage current on the silicon strip detecter is 3.3 micro-amps
    • 32 short SSI cables with Lemo
    • vacuum rated limit switches (data sheet)
  • JLab
    • fADCs
      1. 2 fADC250s on PSC VXS crate
    • 32 coax cables with Lemos on both ends (Fernando). Require 55ft to racks
    • turbo vacuum pump (Tim)

Things to do at ASU

  • packaging, shipping
  • testing(?)

Things to do at JLab

  • preparation of hardware before shipment
  • installation
  • testing with source(?)

Management/Safety

  • write proposal, safety concerns/procedures
  • Get approval from Bert
  • Pass by Patritzia

Analysis Procedures

  • beam requirements
  • requirements on other systems (PS, tagger)
  • analysis procedure
  • online monitoring
  • MC (GEANT?)

Items From Before January 2015