Photon Beam Polarimetry
From GlueXWiki
This page contains a list of to do items for installing the triplet polarimeter for the Spring 2015 GlueX run. Items that used to be on this page are now at the bottom in Items From Before January 2015
Contents
Expected Timeline
- February 2 - 5: (?) Kei visits ASU
- mid-February ship: triplet to JLab
- First week after delivery: Survey by JLab
- February 16 - March 27: installation
- March 28 - April 2: testing
- April 3 - May 4: physics beam
Hardware Division
- ASU
- motor
- HV supply
- JLab
- cables
Things to do at ASU
- packaging, shipping
Things to do at JLab
- preparation of cables
- installation
Management/Safety
- write proposal, safety concerns/procedures
- Get approval from Bert
- Pass by Patritzia
Analysis Procedures
- beam requirements
- requirements on other systems (PS, tagger)
- analysis procedure
- online monitoring
- MC (GEANT?)
Items From Before January 2015
- Studies of some direct photon polarimetry possibility for the meeting on November 1, 2010
- Azimuthal asymmetries from Geant4 polarized pair production on January 10, 2011
- triplet polarimeter presentation at May 2012 collaboration meeting
- July 6 2012 teleconference regarding triplet polarimeter
- Monte Carlo code