Difference between revisions of "Planning for 2015 DIRC Review"

From GlueXWiki
Jump to: navigation, search
Line 6: Line 6:
  
  
== TDR schedule ==
+
== TDR preparation schedule ==
 
* October 5-9: External review at JLab
 
* October 5-9: External review at JLab
 
* September 18: Submit final TDR to external committee
 
* September 18: Submit final TDR to external committee
* September 11: Submit draft TDR to entire collaboration for review
+
* September 11: Submit draft TDR to collaboration for review
 
* August 28: Receive feedback from internal committee's review of TDR
 
* August 28: Receive feedback from internal committee's review of TDR
 
* August 14: Submit draft TDR to internal committee for review
 
* August 14: Submit draft TDR to internal committee for review

Revision as of 12:03, 1 May 2015

Meeting Information

GlueX DIRC Review Meeting
October, 2015


TDR preparation schedule

  • October 5-9: External review at JLab
  • September 18: Submit final TDR to external committee
  • September 11: Submit draft TDR to collaboration for review
  • August 28: Receive feedback from internal committee's review of TDR
  • August 14: Submit draft TDR to internal committee for review
  • August 7: Complete drafts of all TDR sections, one week for editing and consolidating
  • Mid-July: First draft of all TDR sections
  • Early June: Complete outline of TDR sections


Documents


Agenda

TBD