== TDR preparation schedule == | == TDR preparation schedule == | ||
− | * October 5- | + | * October 5-7: External review at JLab |
* September 18: Submit final TDR to external committee | * September 18: Submit final TDR to external committee | ||
* September 11: Submit draft TDR to collaboration for review | * September 11: Submit draft TDR to collaboration for review | ||
* August 28: Receive feedback from internal committee's review of TDR | * August 28: Receive feedback from internal committee's review of TDR | ||
− | * | + | * July 31: Submit draft TDR to internal committee for review |
− | * | + | * July 24: Complete drafts of all TDR sections, one week for editing and consolidating |
− | * | + | * Early July: First draft of all TDR sections |
* Early June: Complete outline of TDR sections | * Early June: Complete outline of TDR sections | ||
Revision as of 15:00, 1 May 2015
Meeting Information
GlueX DIRC Review Meeting
October, 2015
TDR preparation schedule
- October 5-7: External review at JLab
- September 18: Submit final TDR to external committee
- September 11: Submit draft TDR to collaboration for review
- August 28: Receive feedback from internal committee's review of TDR
- July 31: Submit draft TDR to internal committee for review
- July 24: Complete drafts of all TDR sections, one week for editing and consolidating
- Early July: First draft of all TDR sections
- Early June: Complete outline of TDR sections
Documents
- SVN repository for TDR
- Eventually will link to relevant document(s) on DocDB
- Talks for review in DocDB
- etc.
Agenda