Difference between revisions of "RunPeriod-2019-11 Validation"

From GlueXWiki
Jump to: navigation, search
(Physics Production Runs)
(Physics Production Runs)
Line 46: Line 46:
 
|}
 
|}
  
 
+
Up to: 71370
To fix:
+
* 71350 - beam current
+
  
 
=== Notes ===
 
=== Notes ===

Revision as of 10:48, 15 January 2020

Trigger Spreadsheet

December 2019 Run

  • Straight track runs: Starting around 70652, until 70786
  • TOF/CDC HV scans: 70817 - 70828
  • Initial commissioning runs (not everything read out): 70829 - 70834
  • DIRC commissioning runs (no PS): 70835 - 70892
    • Bad TOF HV: 70874 - 70892
    • Lost data: 70850 - 70895
    • TRD/GEM data: 70959 - 70963
  • 2nd round of DIRC commissioning runs (better TOF HV, rocfcal1 restored): 70967-
    • raw mode tests with updated ST firmware: 70995 - 71000
    • production mode with updated ST firmware: 71002 -71206 (?)
    • more firmware fixes on part of the FCAL: 71207 -

2020 Run

Calibration/Tuning

  • Calibration:
    • AMO: 71336, 71344
    • Diamond: 71345, 71346, 71347
    • bad PS settings? it looks like it might be okay, but Sasha said readout thresholds should be optimized
  • Raw mode: 71337
    • short raw mode runs: 71338-71343

Arbitrarily end it here and start production counting. The diamond runs could potentially count as production?

Physics Production Runs

  • Starting at: 71350
0 (PARA) 71354, 71360, 71368, 71370,
90 (PERP) 71355, 71362, 71363, 71369,
45 (PERP) 71353, 71357, 71365, 71372, 71373
135 (PARA) 71350, 71356, 71364, 71371,
AMO 71351, 71352, 71358, 71359

Up to: 71370

Notes

  • junk due to DIRC hole: 71366, 71367
  • CDC noise, should junk: 71360