Difference between revisions of "Run Coordination Meetings:Fall2017 Spring2018 Run"

From GlueXWiki
Jump to: navigation, search
(Hot Checkout)
m (General Information)
Line 56: Line 56:
 
# Nov. 27th-Dec. 1st: Electron beam restoration
 
# Nov. 27th-Dec. 1st: Electron beam restoration
 
# Dec. 1st-Dec. 21st: Hall D Fall run.
 
# Dec. 1st-Dec. 21st: Hall D Fall run.
# Dec. 18th-Jan. 8th: Xmas break. (Solenoid will be ramped down but kept cool)
+
# Dec. 21st-Jan. 8th: Xmas break. (Solenoid will be ramped down but kept cool)
 
# Jan. 9th-Jan. 11th: Electron beam restoration
 
# Jan. 9th-Jan. 11th: Electron beam restoration
 
# Jan. 12th-Mar. 23rd: Hall D Spring run.
 
# Jan. 12th-Mar. 23rd: Hall D Spring run.

Revision as of 08:47, 16 November 2017

Meeting General Agenda

Connect Information

To connect from the outside by phone please do the following

1.) To join via a Web Browser, go to the page [1] https://bluejeans.com/660743227.

2.) To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 660743227.

3.) To join via phone, use one of the following numbers and the Conference ID: 660743227.

4.) The moderator code is 8394

Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

Specific instructions for connecting from JLab's Hall D conference room:

  • Turn polycon on if necessary (do it before turning the computer on)
  • With the polycon, place a call at 199.48.152.152
  • Press # to enable the polycom keypad, then enter the meeting id: 660743227 and #
  • You may have to unmute the microphone: #*4
  • Turn the computer on if needed

Beam and Hall configuration

  • Beam energy expected: 11.640 GeV (Same value as Fall 2016 and Spring 2017).
  • Solenoid on at 1350A. Any field changes should be avoided if possible.
  • CW Beam current:
    • Range: 1 nA-1.5 μA. 250 MHz frequency.
    • Standard production running expected at ~200 nA on 4·10-4 R.L. radiator.
    • RSAD limit for most of the run, excluding high intensity tests: 250 nA on 4·10-4 R.L. radiator.
  • FFB on or Position Slow Lock on (FFB doesn't operate below 50nA).
  • Radiators:
    • Goniometer diamond radiators:
      • J1a50       (50 μm - 4.1·10-4 R.L., 4×4 mm²) - old crystal - excellent rocking curve
      • JD70-100 (58 μm - 4.8·10-4 R.L., 7×7 mm²) - new crystal - excellent rocking curve
      • JD70-105 (47 μm - 3.9·10-4 R.L., 7×7 mm²) - new crystal - good rocking curve
      • JD70-104 (17 μm - 1.4·10-4 R.L., 7×7 mm²) - new crystal - wider rocking curve - marginally usable
    • We also have one 10 μm Al radiator.
    • Amorphous
      • 1.5 µm Al (1.7·10-5 R.L.)
      • 10 µm Al (11.2·10-5 R.L.)
      • 30 µm Al (33.7·10-5 R.L.)
  • Tagger quadrupole on (-4.2 A).
  • Collimator hole: Both 5 mm diameter and 3.4 mm diameter. Default running: 5.0 mm

General Information

This document describes the run plan for the Hall D Fall 2017 and Spring 2018 run.

  • Schedule for the run:
  1. Nov. 27th-Dec. 1st: Electron beam restoration
  2. Dec. 1st-Dec. 21st: Hall D Fall run.
  3. Dec. 21st-Jan. 8th: Xmas break. (Solenoid will be ramped down but kept cool)
  4. Jan. 9th-Jan. 11th: Electron beam restoration
  5. Jan. 12th-Mar. 23rd: Hall D Spring run.
  1. Every Tuesdays: 12h of beam study. Every Thursdays, if necessary: 8h of RF recovery.
  • Accelerator overall plan and priorities:
  1. Deliver physics beam to 4 halls.
  • Experiment: GlueX E12-06-102 Production
  • Planned tests (Accelerator, related to Hall D):
  • Test nA BPM and stripline BPM.
  • Test fast raster operation.
  • Evaluate Rapid Access. Rapid access will be evaluated in Fall and, if successful, will be available for use in Spring. Information on Rapid Access for this run (from T. Whitlatch)
  • Planned tests (Hall D):
    • Align JD70-104 (17 μm - 1.4·10-4 R.L., 7×7 mm²) (Hovanes) ? If possible in Fall 17.
    • Fast raster beam characterization (R. Jones) Will necessitate high-current (??h)
    • Beam halo measurements to assess background for PRad target TAC runs.
    • High-intensity GlueX test (S. Furletov) (??h)
    • TAC V-wire commissioning (Hovanes) (??h)
    • HV CDC and FDC scans. (L. Penchev, Beni Z.)(4h×2)
    • ToF non-linearity test. (Beni Z.) (1h×2 Separated by a few days)
    • Muon chamber test (parasitic?) (E. Smith)
    • TRD test (parasitic) (S. Furletov, L. Penchev)


  • Expected Staffing and responsibilities:
    • The Run Coordinator oversees the commissioning:
      • Nov. 27th-Dec. 1st, 5 days: A. Deur (accelerator restoration)
      • Dec. 1st-Dec. 21st, 20 days: A. Deur
      • Xmas break.
      • Jan. 9th-Jan. 11th, 3 days: A. Deur (accelerator restoration)
      • Jan. 12th-Jan. 24th, 12 days: A. Deur
      • Jan. 24th-Jan. 31st, 7 days: Sasha Ostrovidov
      • Jan. 31st-Feb. 7th, 7 days: Justin Stevens
      • Feb. 7th-Feb. 14th, 7 days: TBD
      • Feb. 14th-Feb. 21st, 7 days: Alex Barnes
      • Feb. 21st-Feb. 28th, 7 days: Zisis Papandreou
      • Feb. 28th-March 7th, 8 days: Cristiano Fanelli
      • March 7th-March 14th, 7 days: Richard Jones
      • March 14th-March 22nd, 8 days: Naomi Jarvis


Runplan

  1. Verify electron beam quality and establish photon beam (assume 1 day).
    • Ion Chambers trip threshold must be set using Al. radiators
    • Tune electron beam with radiator retracted
      • Radiator (amorphous and diamond) must be retracted. Collimator should be in blocking position.
        • Typical levels are (for radiator retracted, collimator fully blocking, electron beam current 50 nA)
          • RAD102_P1 ~ 10 mrad/hr (tagger area, gammas, between tagger and dump)
          • RAD102_P2 ~ 30 mrad/hr (tagger area, gammas, on goniometer).
          • RAD102_P3 ~ 0.1 mrem/hr (tagger area, neutrons, near electronics racks)
          • RAD508_P1 < 0.1 mrad/hr (collimator cave, gammas).
          • RAD508_P2 ~ 0. mrad/hr (Hall. Neutrons).
      • Hall D tagger CARMS, Ion Chamber and BLM threshold for beam trips should not be changed without approval of Hall D leader.
    • Establish good photon beam
    • Make sure tagger quadrupole is on (-4.2 A).
      • Insert 2*10-5 RL radiator. (Call MCC and ask to mask the FSD each time the radiator is moved)
        • Typical levels are (for 2*10-5 radiator, electron beam current 50 nA)
          • RAD102_P1= 15 mrad/hr (tagger area, gammas, between tagger and dump)
          • RAD102_P2= 30 mrad/hr (tagger area, gammas, on goniometer)
          • RAD102_P3= ~2 mrem/hr (tagger area, neutrons, near electronics racks)
          • RAD508_P1= ~10 mrad/hr (collimator cave, gammas).
          • RAD508_P2 < ~ 0. mrad/hr (Hall. Neutrons).
    • Once radiation levels are good, proceed with harp scans (Hovanes/Todd. 15 min)
      • Take tagger harp scans. Check consistency with Accelerator's harps. Study beam focusing
    • Radiation level study (1h):
      • Run 5 min without radiator (Call MCC and ask to mask the FSD each time the radiator is moved). Beam current: 50nA. Repeat at 100 nA and 200 nA
      • Run 5 min with the 10-4 radiator (Call MCC). Beam current: 50nA. Repeat at 100 nA and 200 nA
      • Run 3 min with the 3*10-4 radiator (Call MCC). Beam current: 50nA. Repeat at 100 nA and 200 nA
    • Active Collimator calibration. (20 + 20 mins). Call Hovanes.
      • re-Insert the 10-4 radiator (Call MCC). Use about 100 nA beam current. This will provide the Act. Col. nominal positions for its high gain values.
      • Determine maximum photon beam transmission by doing 2D scans using the collimator x/y motions (Hovanes. 1h)
      • Repeat procedure with 2*10-5 radiator (Call MCC) and 50 nA beam current. This will provide the Act. Col. nominal positions for its low gain values.
      • Record on the white board what is the beam position on 5C11b and Active Collimator for optimal photon transmission, both for low and high Act. Col. gain.
      • Retract profiler.
    • Verify with MCC that position slow lock is back on (locking on Act. Col. and for values corresponding to optimal photon flux).
  2. Detector and beamline checkout.
    • Reestablish L1 trigger Alex. Somov. 3h).
    • Reestablish DAQ (Sergei, 2h).
    • General detector calibration (Sean Dobbs . 4h). Use 10-4 radiator.
      • Run 15 min in Long Mode.
    • From here on, the tasks below are interspersed with data production
  3. Realign 60 μm diamond (JD70-100) Align other diamond(s) later?? (Hovanes, Paul Mattione. 12h/diamond).
  4. Beam background measurements for PRad target TAC runs. (A. Deur/Hovanes/A. Somov) 10-200nA, no radiator, TAC in, target full 15 min runs?? Several runs throughout Fall/Spring run periods.
  5. Straight track run (16h, nominally at the end of the Fall run. Otherwise, end of Spring run) (Lubomir)
    • Ramp down solenoid magnet (2h)
    • Take straight track run data (Lubomir)
  6. Gluex data production
    • Log in run information in the shift summary (make a run list). For each production run, log useful comments on DAQ comment window, see [2]
    • Tagger quadrupole on
    • Harp scans once a day: 15 min.
    • If commissioning and analysis were successful, once a day (?), a beam envelope measurement by rastering on Act. Col. ??min
    • Empty target run every 3 week (2h: 1- h to empty/fill back the target, 1h running). Standard production current.
    • Long mode 10 min run. Once a week (20 min).
    • Amorphous run. Every set of 4 diam. orientation runs. 1h Standard production current. Time to switch from pol. to unpol.: 10min. time to switch from unpol. to pol.: 30min.
    • TAC commissioning, systematic studies and runs. (Hovanes, Alex Somov 2 days.)
      • V-wire commissioning.
      • Move around the collimator with 1mm plug to see effect on TAC. Do 4 different positions.
      • Check effect of material on γ-beam path on TAC: for ex. fill the target (30 min to fill or empty target).
      • Do a TAC run without solenoid field to test GEANT TAC simulation in simpler conditions. (To be done around straight-track runs).
      • Concurrently with the above, 2 TAC runs (one at the beginning, one in the middle of the run). , ??h run with thick converter. 1- LH2 target empty). Use 3.4mm collimator with 1mm plug in (if available).
    • Physics production data with diamonds and 5 mm hole. Ratio of para./transverse/45o/135o data:25/25/25/25. 2h runs and no more, as it may be hard to correct for calibration drifts. Switch polarization every run. Time to switch: 10min. DAQ start run overhead: 3min.
      • Luminosity:
        • Run at about 200 nA (for 60 μm diamond JD70-100).
  1. Parasitic muon chamber
  2. Parasitic TRD run

Hall D white board (current run plan)

Hall D counting room white board

Runplan time charts


Accelerator status

Hot Checkout

  1. Hot Check OUT Status 10% ready ; 0% checked ; 90% not ready

Readiness for Fall 17-Spring18 run

  • Solenoid (Eugene/Beni)
    • 4.5K cold and ready.
    • Tested on 10/27/17: ramped-up twice. First time, solenoid tripped. Then, successfully reached 1350A. It was then ramped-down after 2.5h at this current.
  • Surveys (Tim/Tom)
    • All surveys are done.
  • DAQ (Sergei).
    • Ready for Fall run.
    • Need to start testing with cosmics
  • Trigger (Alex S.)
    • Will start checking boards next week (10/23 - 10/27)
    • Will start checking trigger for μ-chamber.
  • Beam line
    • Diamond status (Tim/Hovanes).
      • Diamond surveyed. Small J1a50 (50 μm) was sent to U.Conn. on Oct. 1st for radiation damage study. New diamonds may be available early Dec. Will be mounted for Spring18 run.
    • Tagger hodoscope (A. Somov)
      • Will be powered and checked next week.
    • Tagger microscope (Alex B./Richard)
      • Need to do voltage check.
    • Goniometer (Hovanes).
      • Λ-wire installed.
      • Motion checked during survey. Need estimate/test/run procedure (Hovanes)
    • Collimator, Active collimator, profiler, flux monitor (Alex B./Hovanes).
      • Need test plan and simulation of data and analysis for raster beam measurement (Richard).
    • PS system (Alex S.)
      • Need to power detector for check.
    • Polarimeter (M. Dugger).
      • Outside SSD not to be connected until Summer 2018.
    • Target (Tim/Alexandre D.)
      • Target was pushed in (10/23 - 10/27). Now in position.
    • TAC (Hovanes)
      • Surveyed. In position. Need to be powered for check.
      • Need to organize special meeting to work out test plans.
    • Slow control (Hovanes).
      • Voltage control for FDC is not working. Fixed
      • One of the FDC mainframes is misbehaving.
    • RF (Elton S.)
    • Radiation monitors
  • Detector systems
    • ST (Mark Ito)
      • In place. Scalers are counting.
    • FDC (Lubomir)
      • One of the mainframes is misbehaving.
      • Off for now.
    • CDC (Beni)
      • Baseline calibration done (10/21-10/28) and check channel baseline alignment. Did it also for FDV
      • No ADC F125 working spare available anymore.
    • BCal (Elton/Mark D.)
      • Testing with LED.
    • FCal (Collin)
      • Was turned on (10/9-10/13). 40 bases replaced.
      • 12 more bases need repair (10/21-10/28). Will discuss this with electronic group.
      • Dearth of spare bases.
    • TOF (Mark Ito/Beni/Alex. Ostrovidov)
      • Need to do HCO.
      • Communication problem with HV crates. 1 HV module was broken. Have to turn TOF on to see if it is fine now.
  • Online monitoring (David L.)
  • Calibration/reconstruction/offline monitoring (Alexander Austregesilo/Thomas B.)
    • Everything should be ready. Will run some checks.
  • muon chamber (Elton S.)
    • Presently (11/02) in the EEL building and being tested there.
    • Crate is in the hall and being connected to main Hall D system.
    • Support structure is being prepared and should be ready by mid-end of Nov.
  • Safety documents (Beni):
    • RSAD and ESAD ready. Will be sent to Bert
    • Question about adding rapid access to safety document.
  • Hall Status/safety (Tom/Tim)
    • Rapid access is progressing and Installation should be ready for the Fall. (But read here)
    • Discussion on what training should be implemented for rapid access? Should add procedure in safety document and send a special email to Hall D collaborations asking to carefully read it.
  • Other topics?
    • Moving to weekly meeting in November?