** Install led shielding wall in front downstream the PS (Tim)  
 
** Install led shielding wall in front downstream the PS (Tim)  
 
** Radiator status (Tim/Hovanes).  
 
** Radiator status (Tim/Hovanes).  
**<strike>Tagger hodoscope (A. Somov)
+
** Tagger hodoscope (A. Somov)
 
*** Repair several counters (re-glue scintillators,check electronics)
 
*** Repair several counters (re-glue scintillators,check electronics)
 
*** Calibrate baseline, run scalers  
 
*** Calibrate baseline, run scalers  

Revision as of 07:58, 21 July 2021

Summer 2021 Run

Meeting General Agenda

Run planning meetings:

Connect Information

To connect from the outside by phone please do the following

1.) To join via a Web Browser, go to the page [1] https://bluejeans.com/660743227.

2.) To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 660743227.

3.) To join via phone, use one of the following numbers and the Conference ID: 660743227.

4.) The moderator code is 8394

Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

Specific instructions for connecting from JLab's Hall D conference room:

  • Turn polycon on if necessary (do it before turning the computer on)
  • With the polycon, place a call at 199.48.152.152
  • Press # to enable the polycom keypad, then enter the meeting id: 660743227 and #
  • You may have to unmute the microphone: #*4
  • Turn the computer on if needed

Beam and Hall configuration

  • Beam energy expected:
    • 11.7 GeV
  • Solenoid:
    • Switched off in the beginning of the run (during most production runs)
    • 1350A during the 3nd week of data taking (TBD after that)
  • CW Beam:
    • 250 MHz frequency
    • 50 - 200 nA (production runs), 400 nA maximum (rate scans), < 5 nA during calibration runs
  • Radiators:
    • Goniometer radiators:
    • Amorphous:
      • 10 µm Al (11.2·10-5 R.L.)
      • 64 µm Al (1.86·10-5 R.L.) calibration
  • Tagger quadrupole on (-4.2 A).
  • Collimator hole: Default running: 5.0 mm.
  • Targets:
    • 4He target: cryogenic target
    • Be target
  • PS converter: 750 μm
  • Miscellaneous:
    • PS test area:
      • Left arm: Check misc. sub-detectors
      • Right arm: Setup to check PbWO4 crystals
    • Other?

General Information

This document describes the run plan for the Hall D Summer 2021 run.

  • Schedule for the run:
  1. August 19: beam restoration
  2. August 20 - October 17: production running
  • Accelerator overall plan and priorities:
  • Hall D plan
    • Experiment:
    • PrimEx
    • TAC Runs?
    • Empty Target Runs
  • Expected Staffing and responsibilities:
    • The Run Coordinator oversees the run:
      • August 19 - September 1: 12 days: Alexandre Deur (accelerator restoration, physics starts August 23)
      • September 1 - September 8: Lubomir Pentchev
      • September 8 - September 15: (Mark Dalton if necessary)
      • September 15 - September 22: Bill Li
      • September 22 - September 29: Igal Jaegle
      • September 29 - October 6: TBD
      • October 6 - October 13: Igal Jaegle
      • October 13 - October 20: Mark Dalton (Last day of Primex running October 16, 3 days accelerator reconfigure, first day of SRC October 20)
      • RC candidates for TBD:
    • The Physics Division Liaison (PDL) and Hall D Work Coordinator/Safety Warden (M. Stevens) verify that the proper safety rules are followed. PDL is:
      • PDL: Lubomir Penchev
    • The analysis coordinator (Alexander Austregesilo) oversees the off-line diagnostic of the different systems and analysis of the data.
    • Shifts: 2 person shifts: 1 local leader and 1 (optionally remote) worker scheduled through the GlueX shift scheduler.
  • Coordination Activities:
    • The RC will attend the MCC meetings at 7:45am and 8:00am and the weekly MCC meeting (Wednesday, 1:30pm). The PDL will attend the weekly MCC meeting.
    • Run meetings: broadcasted on Bluejeans. 8:45am in the counting house conference room. The Run Coordinator will be responsible for organizing and chairing the meeting.
      • Start of run: Daily meetings
      • Production: Alternate nominal length meetings (Monday/Thursday) with short meetings (Tuesday, Wednesday, Friday)

Runplan

Run Plan, Fall 2021

Hall D situation room (current run plan)

Hall D counting room white board

Runplan time charts

Summer 2021 time charts:


Accelerator status

Hot Checkout

To be completed by XXX.

100% ready ; 0% checked ; 0% not ready

Readiness for Summer 2021 Run

  • Solenoid (Eugene/Beni)
    • Test ramp to 300 A the magnet.
    • Start the run without magnetic field
  • Surveys (Tim/Mark)
    • FCAL survey
    • TOF syrvey
    • Survey beamline component (secondary collimator, etc.)
    • Survey CCAL after it's installed in the Hall
  • DAQ (Sergei).
    • Start testing DAQ
    • Power the detector, start taking cosmic data (start in the beginning of August) Needed to power the detectors.
  • Trigger (Alex S.)
    • Start checking LED (random) triggers for sub-detectors
    • Run CCAL trigger when the detector is installed in the Hall
  • Beam line
    • Install He beam pipe between FCAL and CCAL (Tim)
    • Install led shielding wall in front downstream the PS (Tim)
    • Radiator status (Tim/Hovanes).
    • Tagger hodoscope (A. Somov)
      • Repair several counters (re-glue scintillators,check electronics)
      • Calibrate baseline, run scalers
    • Tagger microscope (Richard Jones/Beni)
      • Calibrate baselines, take dark rate data
    • Goniometer (Hovanes).
    • Collimator Motion (Hovanes).
    • Active collimator detectors(Richard Jones/Alexandre Deur)
    • Profiler (Hovanes)
    • luminosity monitor (Hovanes).
    • Halo monitors
      • They have not been touched. They should be ready. To be checked.
    • luminosity monitor
    • PS system (Alex Somov)
      • Check detectors
    • Beam line magnets (PS magnet sweeping magnet and tagger quads).
    • Polarimeter (Sebastian Cole/M. Dugger).
      • Optional, not used in PrimEx
    • Targets (Chris/Tim/Alexandre D.)
      • LH4
      • Be
    • TAC (Hovanes/Alex Somov)
      • Use CCAL as TAC, use as a backup
    • Slow control (Hovanes).
      • Implement new software (features) for FCAL
    • RF (Sergei)
      • Check with cosmic trigger. Looks fine
    • Radiation monitors (Alexandre D.)
      • Operational
  • Detector systems
    • ST (Mark Ito)
      • Ready and tested (Beni)
      • Will be used for DIRC commissioning. Will remain in place for PrimEx-Eta run and used for the 4He run, but will be turned off for the Be part of the run.
      • Random trigger has been implemented (for Beni to monitor neutron radiation damage).
    • FDC (Lubomir)
      • Got cosmic trigger to get data. Things look fine.
      • Gas chromatograph installed near the gas panel. Connected to the FDC and CDD output line.
      • Chiller kept tripping. The problem was fixed by disabling an interlock. The other problem (communication. Maybe due to a IOC) went away. Reason unknown. In all, the chiller is operational.
      • Lights for the camera near the bubbler/rotameter have been set-up (Hall's lights are dimmed because of DIRC).
    • CDC (Beni)
      • Up and running.
      • Flow controller replaced by a rotameter. It will be used from now on instead of the flow controller , unless we understand the origin of the green thing that clogged the flow controller.
    • BCal (Elton/Mark D.)
      • Did LED run on March 29th. It looks good.
      • Will start HCO
      • Low voltages issue (could not turn on) fixed: Two channels had the wrong parameter settings.
    • FCal (Collin Gleason)
      • BCal turned on fine. Need to turn on LED pulser to get some data.
      • One FADC module is dead and two modules have a bad channel. Sasha to replace the bad module on 02/06.
      • HCO done
    • ComCal (Alex Somov)
      • Taking test LED data. They look fine.
    • TOF (Mark Ito/Beni)
      • Ready: It was turned on and looked fine (Beni).
      • Checked baselines with cosmic data.
      • One HV broken was fixed (02/05) by Beni.
    • DIRC (J. Stevens)
      • Fixed a few issues in the box (01/20th).
      • Since 01/24th, everything is connected and readout with low rate trigger looks good.
      • Took high rate (LED) triggers. Looking at it. Need to keep taking LED data to set-up threshold for each channel. LED data will be taken until beam comes.
  • RSAD and ESAD Safety documents (Lubomir):
    • Documents approved and ready for shift takers to sign.
    • DIRC replied ro readiness review recommendations on 01/25th.
    • New ComCal OSP submitted and signed (the previous version expired March 2nd.)
  • Phones
    • System experts should have found their on-call phones by now.
    • System experts should have their phone charged.
    • System experts should start carrying their (charged) phone.
  • Hall Status/safety (Mark/Tim)
  • Other topics?

Live Camera Feeds from the Four Counting Houses

  1. These feeds SHOULD be open and visible at all times from one of the monitors in each of the counting houses.
  2. Management cautions AGAINST opening them from other locations or offsite, out of concern for available bandwidth.

Running Shifts Remote