Run Coordination Meetings:Summer2021
From GlueXWiki
Revision as of 10:47, 8 July 2021 by Shepherd (Talk | contribs) (Created page with "===Summer 2021 Run=== == Meeting General Agenda == Run planning meetings: ==Connect Information== To connect from the outside by phone please do the following 1.) To join...")
Contents
- 1 Summer 2021 Run
- 2 Meeting General Agenda
- 3 Connect Information
- 4 Beam and Hall configuration
- 5 General Information
- 6 Runplan
- 7 Hall D situation room (current run plan)
- 8 Runplan time charts
- 9 Accelerator status
- 10 Hot Checkout
- 11 Readiness for Summer 2021 Run
- 12 Live Camera Feeds from the Four Counting Houses
- 13 Running Shifts Remote
Summer 2021 Run
Meeting General Agenda
Run planning meetings:
Connect Information
To connect from the outside by phone please do the following
1.) To join via a Web Browser, go to the page [1] https://bluejeans.com/660743227.
2.) To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 660743227.
3.) To join via phone, use one of the following numbers and the Conference ID: 660743227.
4.) The moderator code is 8394
Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Specific instructions for connecting from JLab's Hall D conference room:
- Turn polycon on if necessary (do it before turning the computer on)
- With the polycon, place a call at 199.48.152.152
- Press # to enable the polycom keypad, then enter the meeting id: 660743227 and #
- You may have to unmute the microphone: #*4
- Turn the computer on if needed
Beam and Hall configuration
- Beam energy expected:
- Solenoid:
- CW Beam:
- Radiators:
- Goniometer radiators:
- Amorphous:
- Tagger quadrupole on (-4.2 A).
- Collimator hole: Default running: 5.0 mm.
- Targets:
- PS converter: 75 μm
- Miscellaneous:
- PS test area:
- Left arm:
- Right arm:
- Other?
- PS test area:
General Information
This document describes the run plan for the Hall D Summer 2021 run.
- Schedule for the run:
- August : beam restoration
- August XX - October XX: production running
- Accelerator overall plan and priorities:
- Hall D plan
- Experiment:
- PrimEx
- TAC Runs?
- Empty Target Runs
- Expected Staffing and responsibilities:
- The Run Coordinator oversees the run:
- August 19 - August 31: 12 days: Alexandre Deur (accelerator restoration)
- September 1 - September 7: Igal Jagle
- September 8 - September 14: TBD
- September 15 - September 21: TBD
- September 22 - September 28: TBD
- September 29 - October 5: TBD
- October 6 - October 12: TBD
- October 13 - October 21: TBD
- The Run Coordinator oversees the run:
- The Physics Division Liaison (PDL) and Hall D Work Coordinator/Safety Warden (M. Stevens) verify that the proper safety rules are followed. PDL is:
- PDL: Lubomir Penchev
- The analysis coordinator (Alexander Austregesilo) oversees the off-line diagnostic of the different systems and analysis of the data.
- Shifts: 2 person shifts: 1 local leader and 1 (optionally remote) worker scheduled through the GlueX shift scheduler.
- The Physics Division Liaison (PDL) and Hall D Work Coordinator/Safety Warden (M. Stevens) verify that the proper safety rules are followed. PDL is:
- Coordination Activities:
- The RC will attend the MCC meetings at 7:45am and 8:00am and the weekly MCC meeting (Wednesday, 1:30pm). The PDL will attend the weekly MCC meeting.
- Run meetings: broadcasted on Bluejeans. 8:45am in the counting house conference room. The Run Coordinator will be responsible for organizing and chairing the meeting.
- Start of run: Daily meetings
- Production: Alternate nominal length meetings (Monday/Thursday) with short meetings (Tuesday, Wednesday, Friday)
- Useful links:
- Accelerator schedule
- Link to Richard Jones program to plot the beam profile at the collimator.
- Links to previous runplans
- Web-accessible EPICS information
- Links to beam parameters/radiation level monitoring:
- Last 8-hours plots showing 1-minute, 10-minute, and hourly averages
- Same but Last 24-hours
- Same but Last 72-hours
- Week, month, and quarter (3 months) plots also exist, with similar web addresses.
- A map of the radiation monitors
Runplan
Hall D situation room (current run plan)
Hall D counting room white board
Runplan time charts
Summer 2021 time charts:
Accelerator status
- Link to accelerator short term schedule (White board)
- Link to accelerator SAD calendar
- Bluejeans code for the daily MCC meetings and Wednesday 1:30 meeting: 569476853
Hot Checkout
To be completed by XXX.
100% ready ; 0% checked ; 0% not ready
Readiness for Summer 2021 Run
Live Camera Feeds from the Four Counting Houses
- These feeds SHOULD be open and visible at all times from one of the monitors in each of the counting houses.
- Management cautions AGAINST opening them from other locations or offsite, out of concern for available bandwidth.