Difference between revisions of "Run Coordination Meetings: Fall 2014"

From GlueXWiki
Jump to: navigation, search
(Meeting General Agenda)
(Meeting General Agenda)
Line 28: Line 28:
  
 
== Meeting General Agenda ==
 
== Meeting General Agenda ==
<span style="color:red"> Sept. 26th 2014 meeting </span>  
+
<span style="color:red"> Sept. 29th 2014 meeting </span>  
 
# Report relevant updates from 7:50 and 8:00 daily MCC meetings:  
 
# Report relevant updates from 7:50 and 8:00 daily MCC meetings:  
 
#*Accelerator schedule:  
 
#*Accelerator schedule:  
 
#** Accelerator is aiming to start beam restoration on Oct. 3rd and start running 5.5 pass/10 GeV on Oct. 7th. This means locking the Hall around Oct. 10th.
 
#** Accelerator is aiming to start beam restoration on Oct. 3rd and start running 5.5 pass/10 GeV on Oct. 7th. This means locking the Hall around Oct. 10th.
# Report on Work in the Hall today
+
# Report on Work in the Hall
 
#* Hall D is now a radiation aread. OSL need to be worn wherever you go in Hall D.
 
#* Hall D is now a radiation aread. OSL need to be worn wherever you go in Hall D.
 +
#* Elton will conduct a SAF113 training on Friday early afternoon.
 
# Report on yesterday Hall D related events
 
# Report on yesterday Hall D related events
 
# [https://accweb.acc.jlab.org/hco/reports/overall-status?destinationId=9&systemId=&regionId=29&groupId= Hot Check OUT Status]  
 
# [https://accweb.acc.jlab.org/hco/reports/overall-status?destinationId=9&systemId=&regionId=29&groupId= Hot Check OUT Status]  
Line 43: Line 44:
 
#*<span style="color:red"> Profile monitors - </span>
 
#*<span style="color:red"> Profile monitors - </span>
 
#** <strike> The two profilers are now installed. The upstream profiler (collimator cave) is reconnected. </strike>
 
#** <strike> The two profilers are now installed. The upstream profiler (collimator cave) is reconnected. </strike>
#**Upstream profiler is wired. Hovanes can read scalers from it. Downstream profiler not cables yet. Hovanes would like to use a source to identify the left/right and up/down signals.  
+
#**Upstream profiler is wired. Hovanes can read scalers from it. Downstream profiler not cables yet. Hovanes useed a source to identify the left/right and up/down signals. The wiring is correct.  
 
#*<span style="color:red">Active collimator</span> -  
 
#*<span style="color:red">Active collimator</span> -  
 
#** <strike> Cables are terminated and in the Hall.  All hardware work is completed. </strike>
 
#** <strike> Cables are terminated and in the Hall.  All hardware work is completed. </strike>
#** Plexiglas shield is finished. Trent will connect signals cable today and test the signal readout.
+
#** Trent will label the signals cable today and Alex B. will connect them and test the signal readout.
 
#*<strike>  <span style="color:red">Target/Start Counter</span> </strike>  
 
#*<strike>  <span style="color:red">Target/Start Counter</span> </strike>  
 
#** <strike> The light leaks of the SC are largely fixed. SC is mounted back. </strike>
 
#** <strike> The light leaks of the SC are largely fixed. SC is mounted back. </strike>
 
#*<span style="color:red">Tagger shielding</span> - We should have the wall (final labyrinth configuration) mounted by Oct 10th.
 
#*<span style="color:red">Tagger shielding</span> - We should have the wall (final labyrinth configuration) mounted by Oct 10th.
 
#*<strike><span style="color:red">Pair Spectrometer Magnet remote control</span> -  Control is now working. Hysteresis procedure will be done by hand. </strike>
 
#*<strike><span style="color:red">Pair Spectrometer Magnet remote control</span> -  Control is now working. Hysteresis procedure will be done by hand. </strike>
#*<span style="color:blue">Pair Spectrometer Magnet Field readout</span> Hall probe is here and will be installed by Wes. We should have a field reading for the commissioning.
+
#*<span style="color:blue">Pair Spectrometer Magnet Field readout</span> Hall probe is here and will be installed by Wes. We should have a field reading for Oct. 10th.
 
#*Survey:
 
#*Survey:
 
#** <strike><span style="color:red"> FDC </span> </strike>
 
#** <strike><span style="color:red"> FDC </span> </strike>
 
#** <strike><span style="color:red"> Collimator </span> </strike>
 
#** <strike><span style="color:red"> Collimator </span> </strike>
 
#** <strike><span style="color:red">  Pair Spectrometer detector: finishing today. </span> </strike>
 
#** <strike><span style="color:red">  Pair Spectrometer detector: finishing today. </span> </strike>
#** <span style="color:red">Profiler: <strike> 1st profiler surveyed. </strike> Downstream profiler near beam dump to be surveyed Friday. </span> <span style="color:blue"> Downstream profiler when located in front of Solenoid. Will be done next week after Havanes moves it there </span>
+
#** <span style="color:red"><strike> Profilers </strike> </span> <span style="color:blue"> Downstream profiler when located in front of Solenoid. Will be done next week after Havanes moves it there </span>
 
#** <strike><span style="color:red">Start counter: Survey should be done by the end of the day.</span> </strike>
 
#** <strike><span style="color:red">Start counter: Survey should be done by the end of the day.</span> </strike>
 
#** <span style="color:red">FCal: Still working on it. Should be completed today</span>
 
#** <span style="color:red">FCal: Still working on it. Should be completed today</span>
 
#** <span style="color:red">CDC: Should be completed (confirmation?). </span>
 
#** <span style="color:red">CDC: Should be completed (confirmation?). </span>
#**<span style="color:blue">Microscope: Possibly early next week.</span>
+
#**<span style="color:blue">Microscope: Wednesday.</span>
#*<span style="color:red">Vacuum</span> - On schedule. The last piece of beam pipe (the one after the Pair Spec.) will be mounted today.
+
#** <span style="color:red"> Beam pipe section, after the pair spec.</span>
#*<span style="color:red">Amorphous Radiators</span> -  FSD done. Only remaining task is to test FSD.
+
#*<span style="color:red">Vacuum</span> - On schedule. The last piece of beam pipe (the one after the Pair Spec.) was mounted Friday.
 +
#*<span style="color:red">Amorphous Radiators</span> -  FSD done. Will be tested today.
 
#*<span style="color:blue">Halo Counters</span> - All are installed and connected, except the ones in front of solenoid.
 
#*<span style="color:blue">Halo Counters</span> - All are installed and connected, except the ones in front of solenoid.
#*<span style="color:blue">Microscope</span> -  Microscope is in its correct position. Needed to remove a few hodoscope segments to do it.
+
#*<span style="color:blue">Microscope</span> -  Microscope is in its correct position.
 
#*<strike><span style="color:blue">Tagger crates</span> - Can now been readout. </strike>
 
#*<strike><span style="color:blue">Tagger crates</span> - Can now been readout. </strike>
#*<span style="color:blue">Hodoscope checks</span> - The few hodoscope segments that have been removed to install the microscope will be placed back today. Nathan is testing the detectors and electronics with DAQ. 88 (out of ~200) counters have been checked directly with a scope. Nathan will continue to check the rest of them. 4 out of 88 counters have problems (1 not responsive, 3 with cabling problems) and need to be fixed.
+
#*<span style="color:blue">Hodoscope checks</span> - The few hodoscope segments that have been removed to install the microscope were placed back. Nathan is testing the detectors and electronics with DAQ. 120 (out of ~200) counters have been checked directly with a scope. Nathan will continue to check the rest of them. 4 out of 120 counters have problems (1 not responsive, 3 with cabling problems) and need to be fixed.
#* <span style="color:red">Radiation monitors</span> - The gamma probe in the collimator cave is installed. Readout gui to be made. The 2 gamma and the 1 neutron probes are in the Tagger Hall. About 30 min of work left. Waiting for the final positioning <span style="color:blue"> and shielding  </span> of the microscope before finalizing the work. Dan Sexton has installed all the Ion Chambers yesterday. Alexandre D. will verify their positions today.
+
#* <span style="color:red">Radiation monitors</span> - The gamma probe in the collimator cave is installed. Readout gui to be made. The 2 gamma and the 1 neutron probes are in the Tagger Hall. About 30 min of work left. Will be installed tomorrow. Dan Sexton has installed all the Ion Chambers but one is not at the right location. This is being fixed.
 
#*<span style="color:green">2nd sweep magnet. (2nd collimator aperture)</span> - not required for Fall run.  
 
#*<span style="color:green">2nd sweep magnet. (2nd collimator aperture)</span> - not required for Fall run.  
 
# Specific safety notice (from Tom/Tim/Mark):
 
# Specific safety notice (from Tom/Tim/Mark):

Revision as of 14:44, 29 September 2014

General information

Daily Meetings, 8:45am, Hall D conference room. Held by the Run Coordinator. Present Run Coordinator: Alexandre Deur

Connect Information

To connect from the outside by phone please do the following

1.) To join via a Web Browser, go to the page [1] https://bluejeans.com/660743227.

2.) To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 660743227.

3.) To join via phone, use one of the following numbers and the Conference ID: 660743227.

4.) The moderator code is 8394

Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

4.) More information on connecting to bluejeans is available. The old ESNET and SeeVough Information is archived here.

Specific instructions for connecting from JLab's Hall D conference room:

  • Turn polycon on if necessary (do it before turning the computer on)
  • With the polycon, place a call at 199.48.152.152
  • Press # to enable the polycom keypad, then enter the meeting id: 660743227 and #
  • You may have to unmute the microphone: #*4
  • Turn the computer on if needed

Meeting General Agenda

Sept. 29th 2014 meeting

  1. Report relevant updates from 7:50 and 8:00 daily MCC meetings:
    • Accelerator schedule:
      • Accelerator is aiming to start beam restoration on Oct. 3rd and start running 5.5 pass/10 GeV on Oct. 7th. This means locking the Hall around Oct. 10th.
  2. Report on Work in the Hall
    • Hall D is now a radiation aread. OSL need to be worn wherever you go in Hall D.
    • Elton will conduct a SAF113 training on Friday early afternoon.
  3. Report on yesterday Hall D related events
  4. Hot Check OUT Status
  5. Installation punch list (items in red: must by Oct 6th ; Blue: Done by 2nd Fall run; Green: Nice to have it
    • Pair converter
      • The wire is installed. Tom measured the wire diameter without insulation to be 200 microns.
      • Chamber is closed and under vacuum, leak-checked and ready to go.
    • Pair spectrometer detector - Positioned on the stand. Survey is done.
    • Profile monitors -
      • The two profilers are now installed. The upstream profiler (collimator cave) is reconnected.
      • Upstream profiler is wired. Hovanes can read scalers from it. Downstream profiler not cables yet. Hovanes useed a source to identify the left/right and up/down signals. The wiring is correct.
    • Active collimator -
      • Cables are terminated and in the Hall. All hardware work is completed.
      • Trent will label the signals cable today and Alex B. will connect them and test the signal readout.
    • Target/Start Counter
      • The light leaks of the SC are largely fixed. SC is mounted back.
    • Tagger shielding - We should have the wall (final labyrinth configuration) mounted by Oct 10th.
    • Pair Spectrometer Magnet remote control - Control is now working. Hysteresis procedure will be done by hand.
    • Pair Spectrometer Magnet Field readout Hall probe is here and will be installed by Wes. We should have a field reading for Oct. 10th.
    • Survey:
      • FDC
      • Collimator
      • Pair Spectrometer detector: finishing today.
      • Profilers Downstream profiler when located in front of Solenoid. Will be done next week after Havanes moves it there
      • Start counter: Survey should be done by the end of the day.
      • FCal: Still working on it. Should be completed today
      • CDC: Should be completed (confirmation?).
      • Microscope: Wednesday.
      • Beam pipe section, after the pair spec.
    • Vacuum - On schedule. The last piece of beam pipe (the one after the Pair Spec.) was mounted Friday.
    • Amorphous Radiators - FSD done. Will be tested today.
    • Halo Counters - All are installed and connected, except the ones in front of solenoid.
    • Microscope - Microscope is in its correct position.
    • Tagger crates - Can now been readout.
    • Hodoscope checks - The few hodoscope segments that have been removed to install the microscope were placed back. Nathan is testing the detectors and electronics with DAQ. 120 (out of ~200) counters have been checked directly with a scope. Nathan will continue to check the rest of them. 4 out of 120 counters have problems (1 not responsive, 3 with cabling problems) and need to be fixed.
    • Radiation monitors - The gamma probe in the collimator cave is installed. Readout gui to be made. The 2 gamma and the 1 neutron probes are in the Tagger Hall. About 30 min of work left. Will be installed tomorrow. Dan Sexton has installed all the Ion Chambers but one is not at the right location. This is being fixed.
    • 2nd sweep magnet. (2nd collimator aperture) - not required for Fall run.
  6. Specific safety notice (from Tom/Tim/Mark):