Run Coordination Meetings: Fall 2014

From GlueXWiki
Revision as of 07:02, 6 October 2014 by Deurpam (Talk | contribs) (Meeting General Agenda)

Jump to: navigation, search

General information

Daily Meetings, 8:45am, Hall D conference room. Held by the Run Coordinator. Present Run Coordinator: Alexandre Deur

Connect Information

To connect from the outside by phone please do the following

1.) To join via a Web Browser, go to the page [1] https://bluejeans.com/660743227.

2.) To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 660743227.

3.) To join via phone, use one of the following numbers and the Conference ID: 660743227.

4.) The moderator code is 8394

Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

4.) More information on connecting to bluejeans is available. The old ESNET and SeeVough Information is archived here.

Specific instructions for connecting from JLab's Hall D conference room:

  • Turn polycon on if necessary (do it before turning the computer on)
  • With the polycon, place a call at 199.48.152.152
  • Press # to enable the polycom keypad, then enter the meeting id: 660743227 and #
  • You may have to unmute the microphone: #*4
  • Turn the computer on if needed

Meeting General Agenda

Oct 3rd 2014 meeting

  1. Report relevant updates from 7:50 and 8:00 daily MCC meetings:
    • Accelerator schedule: Aiming to start beam restoration on Oct. 7th and start running 5.5 pass/10 GeV on Oct. 10th. This means locking the Hall around Oct. 13th.
  2. Report on Work in the Hall:
    • The upstream platform is now a hearing protection area. Hall D is a radiation aread. OSL need to be worn everywhere in Hall D.
    • There will be a power outage of at least 2h next week (precise date TBD).
  3. Report on yesterday Hall D related events
  4. Hot Check OUT Status 16% ready ; 18% checked ; 66% not ready
  5. Installation punch list (items in red: must by Oct 6th ; Blue: Done by 2nd Fall run; Green: Nice to have it
    • Pair converter
      • The wire is installed. Tom measured the wire diameter without insulation to be 200 microns.
      • Chamber is closed and under vacuum, leak-checked and ready to go.
    • Pair spectrometer detector - Positioned on the stand. Survey is done.
    • Profile monitors -
      • The two profilers are now installed and surveyed.
    • Active collimator -
      • <strike> Cables are terminated and in the Hall. All hardware work is completed.
      • Fully cabled now. Need to check if the cables are long enough when the collimator is translated.
    • Target/Start Counter
      • The light leaks of the SC are largely fixed. SC is mounted back.
    • Tagger shielding - Wall (final labyrinth configuration) 50% complete. Should be complete by Oct 9th. Small walls to by erected soon after.
    • Pair Spectrometer Magnet remote control - Control is now working. Hysteresis procedure will be done by hand.
    • Pair Spectrometer Magnet Field readout Hall probe is here and will be installed by Wes. Wes is working on cabling. The gui is done.
    • Survey:
      • FDC
      • Collimator
      • Pair Spectrometer detector: finishing today.
      • Upstream Profiler in collimator cave.
      • Start counter: Survey should be done by the end of the day.
      • FCal: Still working on it. Should be completed today
      • CDC: Should be completed (confirmation?).
      • Microscope
      • Beam pipe section
    • Vacuum - On schedule.
    • Amorphous Radiators - FSD done and tested.
    • Halo Counters - All are installed and connected.
    • Microscope - Microscope is in its correct position. Being cabled.
    • Tagger crates - Can now been readout. Will be removed on the 10th.
    • Hodoscope checks - Nathan is testing the detectors and electronics with DAQ. 131 (out of ~200) counters have been checked directly with a scope. Nathan will continue to check the rest of them. Some signs of light leaks. 9 out of 131 counters have problems (1 not responsive, 8 with cabling problems) and need to be fixed.
    • Radiation monitors - Gamma and neutron probes ready. Readout gui to be made. Ion Chambers installed but one is not at the right location. This is being fixed. Witness SiPM baseline characterization: waiting for Sacha.
    • 2nd sweep magnet. (2nd collimator aperture) - not required for Fall run.
  6. Specific safety notice (from Tom/Tim/Mark): Tagger Hall: Be mindful of the wall construction work, in particular the forklift motions.