(Created page with "RC summary September 23 - September 29, 2021 There was no beam for a little bit more than half of the week. We lost 4 hours when the beam was available to debug the tagger mi...")
 
 
Line 1: Line 1:
 
RC summary September 23 - September 29, 2021
 
RC summary September 23 - September 29, 2021
  
There was no beam for a little bit more than half of the week. We lost 4 hours when the beam was available to debug the tagger microscope (there was a wrong cabling issue). During the downtime, a dozen FCAL channels were required to be debugged, by either replacing a PMT or more frequently a base. During this week, the PrimEx physics production started with Be target (50 nA) and CDC & FDC turn on aka FDC straight track run for 2.5 shifts. Then, we continue for 2 shifts to take data with the chambers off and the beam current increased to 100 nA. Finally, we started the 10 shifts chunk of 200 nA Be data set.
+
There was no beam for a little bit more than half of the week. We lost 4 hours when the beam was available to debug the tagger microscope (there was a wrong cabling issue). During the downtime, a dozen FCAL channels were required to be debugged, by either replacing a PMT or more frequently a base. Throughout the week, HV was changed in different detectors: TOF, TAGM & FCAL. During this week, the PrimEx physics production started with Be target (50 nA) and CDC & FDC turn on aka FDC straight track run for 2.5 shifts. Then, we continue for 2 shifts to take data with the chambers off and the beam current increased to 100 nA. Finally, we started the 10 shifts chunk of 200 nA Be data set.

Latest revision as of 14:31, 13 October 2021

RC summary September 23 - September 29, 2021

There was no beam for a little bit more than half of the week. We lost 4 hours when the beam was available to debug the tagger microscope (there was a wrong cabling issue). During the downtime, a dozen FCAL channels were required to be debugged, by either replacing a PMT or more frequently a base. Throughout the week, HV was changed in different detectors: TOF, TAGM & FCAL. During this week, the PrimEx physics production started with Be target (50 nA) and CDC & FDC turn on aka FDC straight track run for 2.5 shifts. Then, we continue for 2 shifts to take data with the chambers off and the beam current increased to 100 nA. Finally, we started the 10 shifts chunk of 200 nA Be data set.