We were scheduled for 157 hours (24 * 7 - 7h RF recovery - 4h beam study) of beam this week. CW beam on target was 72.7 hours, and Acceptable Beam in Use was 69.9 hours. We lost in total 8.7 hours of the usable beam time. Apart from the standard radiator change and DAQ start/stop which took 3.8 hours, we used 3 hours for the hall access for DIRC de-installation. Also, invasive access for repair of detector voltages (TRD, BCAL) cost 1.9 hours.
 
We were scheduled for 157 hours (24 * 7 - 7h RF recovery - 4h beam study) of beam this week. CW beam on target was 72.7 hours, and Acceptable Beam in Use was 69.9 hours. We lost in total 8.7 hours of the usable beam time. Apart from the standard radiator change and DAQ start/stop which took 3.8 hours, we used 3 hours for the hall access for DIRC de-installation. Also, invasive access for repair of detector voltages (TRD, BCAL) cost 1.9 hours.
 +
 +
As for DIRC commissioning, we've finished taking straight-track data for GEM/TRD at 10am on Thu, 09/03/2020, and utilized the scheduled 7h downtime (RF recovery) to ramp up the solenoid magnet. After that, field-on data for GEM/TRD were collected overnight. During the de-installation work in the morning on Fri, 09/04/2020, Nick successfully replaced the TagM preamp to fix long-lasting TAGM missing channels (4-6) problem.

Revision as of 20:02, 10 September 2020

RC summary, 09/02/2020 - 09/09/2020, Keigo Mizutani

This week started during Summer 2020 DIRC Commissioning, and we resumed standard data production on Fri, 09/04/2020. This week, we collected ~13.5B triggers for production.

We were scheduled for 157 hours (24 * 7 - 7h RF recovery - 4h beam study) of beam this week. CW beam on target was 72.7 hours, and Acceptable Beam in Use was 69.9 hours. We lost in total 8.7 hours of the usable beam time. Apart from the standard radiator change and DAQ start/stop which took 3.8 hours, we used 3 hours for the hall access for DIRC de-installation. Also, invasive access for repair of detector voltages (TRD, BCAL) cost 1.9 hours.

As for DIRC commissioning, we've finished taking straight-track data for GEM/TRD at 10am on Thu, 09/03/2020, and utilized the scheduled 7h downtime (RF recovery) to ramp up the solenoid magnet. After that, field-on data for GEM/TRD were collected overnight. During the de-installation work in the morning on Fri, 09/04/2020, Nick successfully replaced the TagM preamp to fix long-lasting TAGM missing channels (4-6) problem.