RC weekly summary for Nov 2- Nov 9


We started the week with Maintenance day on Wednesday and got the beam back on the Swing shift. We had the common FCAL voltage issues and base replacement. After Harp scans, we restarted production running on Full target. We emptied the target cell on Thursday morning and continued taking empty target production data until Saturday morning. We filled the target cell on Saturday morning with no problems and continued taking production data on Full target until the end of the RC shift. Accelerator had issues during the weekend, and some runs were marked when the accelerator was troubleshooting problems with the injector.

This week's accelerator efficiency was about 62%, with ~4 hours of BANU due mainly to DAQ overhead.