Run Coordinator report: winter 2023 w2

From GlueXWiki
Revision as of 09:37, 29 January 2023 by Deurpam (Talk | contribs) (Created page with "= Wednesday January 24 = === Past 24 hours === * Beam study, with Hall D access. Then, production on diamond. ABU= 12.2 h for the day. === Shift Reports === * [https://logboo...")

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Wednesday January 24

Past 24 hours

  • Beam study, with Hall D access. Then, production on diamond. ABU= 12.2 h for the day.

Shift Reports

Reports

Issues

Plans

  • Production (300 nA, 2h runs) with cycle:
    • 2 runs para(0/90)
    • 2 runs perp(0/90)
    • 2 runs para(45/135)
    • 2 runs perp(45/135)
    • 1 run amo (use it to rejuvenate amo reference in CBREM GUI)
  • Trigger fine tuning Thursday? (A. Somov)

Tuesday January 24

Past 24 hours

  • Production on diamond. Trippy beam, but good availability. ABU=16.2h for the day

Shift Reports

Reports

Issues

Plans

  • 4h of beam studies + 2h beam restoration). Tagger and Hall to be surveyed around 9pm:
    • Safety Walkthrough (M. Dalton + trainee(s))?
    • Scot to access to take out Vlad's chiller
    • Tagger access for HV communication issue?
    • Investigate the faulty pressure sensor?
    • Chris Carlin to fix the target controls
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs para(0/90)
    • 2 runs perp(0/90)
    • 2 runs para(45/135)
    • 2 runs perp(45/135)
    • 1 run amo

Monday January 23

Past 72 hours

  • Beam was off from Friday 7:30am to Saturday 2am due to vacuum issue in south linac. Friday ABU: 4.0h
  • Saturday: Ran on amorphous (goni), 300 nA. Until Sunday 9am when Hovanes started diamond alignment. Saturday ABU: 18.6h
  • Sunday 9am-5:30pm: diamond alignment. Sunday 8:30pm - Monday 7:30am: First production 0/90/45/135/amo cycle (see CBrem peak). Then did Harp scans. Sunday ABU: 14.3h

Shift Reports

Reports

Issues

Plans

  • Production on amorphous (Goni, 300 nA) until the diamond is aligned.
  • Diamond alignment: Sunday morning, ~9am. (Hovanes)
  • Then production on diamond radiator, 4 orientations + amo. 300 nA. Presently, we do each orientation once (not twice) and each run is nominally 2h, including the amo run.
  • Tomorrow (Tuesday, 24th: 4h of beam studies + 2h beam restoration):
    •  ?Safety Walkthrough (M. Dalton + trainee(s))?
    • Scot to access to take out Vlad's chiller
    •  ?Investigate the faulty pressure sensor?
    •  ?Chris Carlin to fix the target controls?
  • Link to runplan

Friday January 20

Past 24 hours

Shift Reports

Reports

Issues

Plans

  • Thursday evening and Friday night:
    • Once beam come back, do Harp scans.
    • FCup test of our beam dump BCM.
    • Run 1h on the amo radiator of the goni (baseline for next runs below). 250 nA
    • Run 2h on 0.19E-4 RL amo radiator on radiator ladder (250 nA).
    • Run 2h on 1.12E-4 RL amo radiator on radiator ladder (250 nA).
    • Run (until the beam is taken away in the morning) on 3.4E-4 RL amo radiator on radiator ladder (250 nA).
  • Beam off starting Friday morning around 7:30am to fix vacuum issue in south linac, until 4pm(?).
  • When the beam comes back:
    • Harp scans
    • Production on goni amo radiator at 300 nA until Sunday morning.
  • Hall access:
    • Sergey F.
  • Diamond alignment: Sunday morning, ~9am.
  • Until then production on amorphous.
  • Link to runplan



The main task during the RC week from 01/18-01/25/2023 was to align the diamond and start then production with linearly polarized photons. The diamond was aligned on Sunday (01/22/2023) and production started right after. The reason why alignment could not be done sooner is because of multiple issues with the accelerator. Wednesday, the beam was not available during the day for beam and RF study and a long recovery from these study: acceptable beam came back only Thursday at 1:10am. Hovanes, the expert aligning the diamond waited until 1am and left as the beam was still not there and it was getting too late to do the long work efficiently. We therefore took amorphous data in production configuration when the beam. Thursday, the

and Friday.

The other special task done during the week (waiting for the aligned diamond to become available) was a long empty target run done during the Tueaday-Wednesday night. Its analysis shows the expected vertex distribution.

A significant issue discovered during the week was that the calibration of our BCM differed by 30% compared to the run in 2020. Discussions with Ops revealed that the BCM calibration (called BLA calibration) is not done systematically before each run period and the last one was done in 2021. We discussed with Ops to ensure that it should now be done at each start of new run period.


Plans

  • Beam off starting around 10am for RF study, nominally until 4pm+/-4h.
  • Hall in controlled access?
  • Diamond alignment: Friday day ? (Hovanes unavailable today)
  • Until Friday day, production on amorphous?
  • Link to runplan