Run Coordination report for the week from 02/01-02/08/2023 (Hovanes Egiyan).

The main focus of this week was production running on diamond and amorphous radiator. Due to accelerator-related issues and Hall D Pair Spectrometer magnet power supply failure we only claimed 37.1h of ABU time. The BANU time for last week was 15.2h, PSPEC-related activities were responsible for 11.3f of these BANU hours. We performed a high beam current test during which we reached 950nA beam current.

We have the following issues during the last week:

  • Issues with the TAGH HV module
  • PSPEC magnet power supply