=== Plan === | === Plan === | ||
* Continue with Full target production. | * Continue with Full target production. | ||
+ | * Accelerator maintenance scheduled for Tuesday or Wednesday. |
Revision as of 09:23, 10 November 2022
Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Back to Run Coordination Meetings:Fall2022
Thursday, November 10
Past 24 hours
- No beam for ~14 hours (5:15-19:30) due to beam tuning and cryomodule issues.
- Did harp scan when the beam was back during swing shift https://logbooks.jlab.org/entry/4079511. The sigmas of u and y positions at radiator were somewhat larger and lie outside the preferred range, monitoring PS rates.
- Took production data on Full LHe target. Since yesterday we collected 1.0 B events.
Shift Summary
Issues/Reports
- No beam for ~14 hours due to beam tuning issues, followed by issues with some of the cryomodules.
Plan
- Continue with Full target production.