Difference between revisions of "Run Planning Meeting Noters, November 9- November 16, 2022"

From GlueXWiki
Jump to: navigation, search
(Wednesday, November 9)
(Shift Summary)
Line 17: Line 17:
  
  
* [https://logbooks.jlab.org/entry/4078571 Day Nov 8 ]
+
* [https://logbooks.jlab.org/entry/4078571 Day Nov 9 ]
* [https://logbooks.jlab.org/entry/4078809 Swing Nov 8]
+
* [https://logbooks.jlab.org/entry/4078809 Swing Nov 9]
* [https://logbooks.jlab.org/entry/4078915 Owl Nov8/9]
+
* [https://logbooks.jlab.org/entry/4078915 Owl Nov9/10]
* [https://logbooks.jlab.org/entry/4079038 Early riser Nov 9]
+
* [https://logbooks.jlab.org/entry/4079038 Early riser Nov 10]
  
 
=== Issues/Reports ===
 
=== Issues/Reports ===

Revision as of 12:49, 9 November 2022

Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Hall D Logbook

Back to Run Coordination Meetings:Fall2022

Thursday, November 10

Past 24 hours

  • Taking production data on Full LHe target whenever we had beam. Since yesterday we collected 1.9 B events.

Shift Summary

Issues/Reports

  • No beam for ~7 hours due to beam tuning issues, followed by issues with some of the cryomodules.

Plan