=Saturday, November 12=
 
=Saturday, November 12=
 
=== Past 24 hours ===
 
=== Past 24 hours ===
* Took production data on Full LHe target. When the beam was gone we switched to empty target. Since yesterday we collected 2.2 B events.
+
* Took production data on Full LHe target.  
 +
When the beam was gone we switched to empty target. Since yesterday we collected 2.2 B events.
  
 
=== Shift Summary ===
 
=== Shift Summary ===

Revision as of 09:04, 12 November 2022

Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Hall D Logbook

Back to Run Coordination Meetings:Fall2022

Thursday, November 10

Past 24 hours

  • No beam for ~14 hours (5:15-19:30) due to beam tuning and cryomodule issues.
  • Did harp scan when the beam was back during swing shift https://logbooks.jlab.org/entry/4079511. The sigmas of u and y positions at radiator were somewhat larger and lie outside the preferred range, monitoring PS rates.
  • Took production data on Full LHe target. Since yesterday we collected 1.0 B events.

Shift Summary

Issues/Reports

  • No beam for ~14 hours due to beam tuning issues, followed by issues with some of the cryomodules.
  • After the beam was back it was mostly stable besides some FSD trips.

Plan

  • Continue with Full target production.
  • Accelerator maintenance scheduled for Tuesday or Wednesday.

Friday, November 11

Past 24 hours

  • Since the beam was not converging as desired we asked accelerator people to tune beam optics for Hall D. After beam tuning MCC did harp scan followed by our harp scans. The sigma u, sigma y and sigma x fits look like they are converging at collimator (https://logbooks.jlab.org/entry/4080101), though sigma u, sigma y from radiator harp scan are still outside of the preferred range. The plan for now is to monitor PSC rates (https://logbooks.jlab.org/entry/4080753).
  • Took production data on Full LHe target. Since yesterday we collected 2.2 B events.

Shift Summary

Issues/Reports

  • MCC took away the beam from 16:36-18:55 to correct steering issues for delivering 70 uA beam to Hall C.
  • Beam energy distribution normalized to a previous run (110641) shows change in beam energy distribution (https://logbooks.jlab.org/entry/4080603). If this is not a problem we just need to update the reference plot.

Plan

  • Continue with Full target production.
  • Accelerator maintenance scheduled for Tuesday ~6:45 am, duration at list a shift and half.


Saturday, November 12

Past 24 hours

  • Took production data on Full LHe target.

When the beam was gone we switched to empty target. Since yesterday we collected 2.2 B events.

Shift Summary

Issues/Reports

  • SRF Vacuum issues, Hall B Solenoid PS Failure. No beam from 14:29-23:04.

Plan

  • Started empty target production when the beam was back.
  • Accelerator maintenance scheduled for Tuesday ~6:45 am, duration at list a shift and half.