Thursday, April 5 at 08:45

  1. Notes from the previous 24 hours:
    • Beam convergence adjustment by Todd
    • Beam issues off and on through Swing and Owl shifts
    • fADC125 module failure in FDC. Rapid access used by Sascha and Cody to replace.
    • Other DAQ issues ~1hr for swing + owl
  2. Issues:
    • Shift-takers should at least log any acknowledged alarms so that they are not forgotten
      • TAGH had few tripped channels with no alarm sounding
    • High Level monitoring plots look bad (calibrations)
    • Bubblers
  3. Reports:
  4. Run Plan
    • TAC run using V-wire today (pending good AC lock)
    • Production Running
  5. AOB