Difference between revisions of "Run Planning Meeting Notes, Apr 19-Apr 25, 2018"

From GlueXWiki
Jump to: navigation, search
(Thursday, April 19 at 08:45)
(Thursday, April 19 at 08:45)
Line 14: Line 14:
 
# Reports:
 
# Reports:
 
#* [https://logbooks.jlab.org/entry/3562987 Results from material scan] (Sergey and Lubomir)
 
#* [https://logbooks.jlab.org/entry/3562987 Results from material scan] (Sergey and Lubomir)
#* Results from thin diamond,  3.4 mm hole. [https://logbooks.jlab.org/entry/3562976 FDC currents drop, not CDC] [https://logbooks.jlab.org/entry/3562958 PS flux comparison ]
+
#* Results from thin diamond,  3.4 mm hole. [https://logbooks.jlab.org/entry/3562976 FDC currents drop, not CDC] [https://logbooks.jlab.org/entry/3562958 PS flux comparison ] [https://logbooks.jlab.org/entry/3563236 PS enhancement increases]
 
#* First results from current scan [https://logbooks.jlab.org/entry/https://logbooks.jlab.org/entry/3563226] [https://logbooks.jlab.org/entry/3563244] [https://logbooks.jlab.org/entry/3563162]
 
#* First results from current scan [https://logbooks.jlab.org/entry/https://logbooks.jlab.org/entry/3563226] [https://logbooks.jlab.org/entry/3563244] [https://logbooks.jlab.org/entry/3563162]
 
#* [https://logbooks.jlab.org/entry/3562880 CDC current correlation with Y beam position observed again] (Beni)
 
#* [https://logbooks.jlab.org/entry/3562880 CDC current correlation with Y beam position observed again] (Beni)
Line 26: Line 26:
 
#* Fast raster scan deferred until the required people can be found
 
#* Fast raster scan deferred until the required people can be found
 
#* Future studies
 
#* Future studies
#** High rate trigger studies
+
#** [https://halldweb.jlab.org/wiki/images/f/fb/Spring18_week15.jpg weekly plan]
 
# AOB
 
# AOB

Revision as of 08:43, 19 April 2018

<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run

Thursday, April 19 at 08:45

  1. Notes from the previous 24 hours:
  2. Issues:
  3. Reports:
  4. Run Plan
    • Access today to
      • Move active collimator to 5 mm hole
      • Attach Pb radiator to profiler
      • Muon chamber inspection
    • Production running
      • Harp scan when beam comes back
    • Fast raster scan deferred until the required people can be found
    • Future studies
  5. AOB