Difference between revisions of "Run Planning Meeting Notes, Apr 26-May 2, 2018"

From GlueXWiki
Jump to: navigation, search
m
m
Line 12: Line 12:
 
#*Low current BPM lock test
 
#*Low current BPM lock test
 
#Issues:
 
#Issues:
#* Rootspy crashes [https://logbooks.jlab.org/entry/3567623]
+
#* Rootspy crashes and recovery [https://logbooks.jlab.org/entry/3567623][https://logbooks.jlab.org/entry/3567838]
 
#* Running with 750 um converter
 
#* Running with 750 um converter
 
# Reports:
 
# Reports:
Line 23: Line 23:
 
#*Sunday
 
#*Sunday
 
#**Production Running
 
#**Production Running
#*Longer term run plan
+
#*Longer term run plan/Other items
 
#**Resumption of raster scan studies
 
#**Resumption of raster scan studies
 +
#**Level 1 trigger studies
 
#*End of run preparation
 
#*End of run preparation
 
#**Be prepared to switch everything off after last beam at 6 am, SUNDAY May 6
 
#**Be prepared to switch everything off after last beam at 6 am, SUNDAY May 6

Revision as of 07:33, 27 April 2018

<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run

Friday, April 27 at 08:45

  1. Notes from the previous 24 hours:
    • Production running
    • BCal Pedestals [1]
    • Low current BPM lock test
  2. Issues:
    • Rootspy crashes and recovery [2][3]
    • Running with 750 um converter
  3. Reports:
  4. Run Plan
    • Friday
      • High rate DAQ tests (9.30 am)
      • TAC Run (2 pm)
    • Saturday
      • Production Running
    • Sunday
      • Production Running
    • Longer term run plan/Other items
      • Resumption of raster scan studies
      • Level 1 trigger studies
    • End of run preparation
      • Be prepared to switch everything off after last beam at 6 am, SUNDAY May 6
  5. AOB

Thursday, April 26 at 08:45

  1. Notes from the previous 24 hours:
    • Replacement of TAGH FDC module [4]
    • Production running
    • High rate trigger tests
  2. Issues:
    • Resuming DAQ after Wednesday tour [5]
    • Running with 750 um converter
    • Hot Channels, delta t offsets [6]
  3. Reports:
  4. Run Plan
    • Thursday
      • Level 1 trigger test
      • High rate trigger test part II(?)
      • Low current BPM lock test (afternoon)
    • Friday
      • High rate DAQ tests (9.30 am)
      • TAC Run (2 pm)
    • Saturday
    • Longer term run plan
  5. AOB