Difference between revisions of "Run Planning Meeting Notes, April 19-April 25, 2016"
From GlueXWiki
Line 6: | Line 6: | ||
==Wednesday, April 20== | ==Wednesday, April 20== | ||
# Accelerator Status | # Accelerator Status | ||
− | #* Overnight running | + | #* Overnight running (reasonably good, lost time for orbit issues due to the Hall A beam and ion chamber issues in the north linac. |
#* Scheduled accelerator down on Wednesday 20 April (7 am - 6 pm) | #* Scheduled accelerator down on Wednesday 20 April (7 am - 6 pm) | ||
#** RF recovery, beam studies, Hall A pass change | #** RF recovery, beam studies, Hall A pass change | ||
# Hall-D/GlueX items | # Hall-D/GlueX items | ||
#* Running overnight | #* Running overnight | ||
− | #** ABUs | + | #** ABUs 14.8 hours in 3 shifts (day 371 mins, Swing 320 mins, owl 200 mins) |
− | #** Triggers | + | #** Triggers (PARA 354M trigs, PERP 375 M trigs) |
#** [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1755888890 Run Statistics] | #** [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1755888890 Run Statistics] | ||
#* Hall D access Wednesday 20 April. | #* Hall D access Wednesday 20 April. |
Revision as of 08:40, 20 April 2016
Wednesday, April 20
- Accelerator Status
- Overnight running (reasonably good, lost time for orbit issues due to the Hall A beam and ion chamber issues in the north linac.
- Scheduled accelerator down on Wednesday 20 April (7 am - 6 pm)
- RF recovery, beam studies, Hall A pass change
- Hall-D/GlueX items
- Running overnight
- ABUs 14.8 hours in 3 shifts (day 371 mins, Swing 320 mins, owl 200 mins)
- Triggers (PARA 354M trigs, PERP 375 M trigs)
- Run Statistics
- Hall D access Wednesday 20 April.
- RadCon has been contacted.
- Access possible in the morning
- Beam studies in the afternoon (upstream slow locks)
- Walkthrough (Hall and Tagger)
- Collimator work
- TRD work
- Magnet work
- FCAL bases exchange
- Microscope gain balancing
- Report on Trigger studies
- Report on TRD studies
- Latest Occupancy Plots look reasonable??
- Running overnight
- Run Plan
- Mode 8 (raw mode) running with cosmics during access
- Production 50 um
- Trigger studies
- TRD studies
- Empty Target run with 5 mm hole (Friday ?)
- TAGM alignment (Friday ?)
- Offline Analysis?
- Any Other Business?
Tuesday, April 19
- Accelerator Status
- Running overnight
- ABUs 16.4 hours in 3 shifts (309 + 328 + 349 minutes)
- Triggers (PARA 462 M, PERP 597 M, Unpolarized 150 M)
- Scheduled accelerator down on Wednesday 20 April (7 am - 6 pm)
- RF recovery, beam studies, Hall A pass change
- Running overnight
- Hall-D/GlueX items
- Report on Trigger studies
- Report on TRD studies
- Hall D access Wednesday 20 April.
- Access possible throughout Day and into Swing, starting about 8 am. RadCon has been contacted.
- No tagger access required???
- Collimator work
- TRD work
- Magnet work
- FCAL bases exchange
- Latest Occupancy Plots look reasonable
- Run Statistics
- Run Plan
- Production 50 um
- Trigger studies
- TRD studies
- Empty Target run with 5 mm hole (Thursday ?)
- TAGM alignment (Thursday ?)
- Mode 8 (raw mode) running?
- Para/Perp luminosity studies?
- Offline Analysis?
- Any Other Business?